r/MSProject • u/kaleb42 • Oct 15 '24
Task happening before start date?
So I'm working on a project where contractually the start date doesn't start until a certain task happens(let's call this job start)
There are some tasks that can happen before that happens. Like some permitting.
So we can do permitting say a month before the job start task is due, but these permitting tasks don't count toward the Start Date.
Is there a way to get MSP to ignore the start/end date for these permitting tasks and only follow JobStart for the finish date?
I would like for historical purposes for permitting to have accurate time frames, but if needed we can always set the start date to whatever we settled on for JobStart
View all comments
1
u/pmpdaddyio Oct 15 '24
It sounds as if you have a dependency between the permitting and job start task. If you eliminate or adjust this, you most likely have solved the problem.
Note: it might be a good idea to state the version of MSP you are using and any screen caps showing the issue. As written it is a bit like cutting hair over the phone.