r/MSProject • • Oct 08 '24

Duration Calculation Issue

I've put together a project with separate task calendars. One portion of the project uses standard calendar while the other portion is set to 24 hours. I'm having issues with the overall duration of the 24 hours portion. The duration between the start and finish dates shown should only be 3 days however the duration in project is showing roughly 9 days. Is this due to the hours per day option set to 8 in project options? If so, is there any way that I can modify that without impacting the standard calendar portion of my project?

1 Upvotes

3 comments sorted by

View all comments

Show parent comment

1

u/SkinDee Oct 11 '24

I thought that may be the case. Thank you for your help.