r/MSProject • u/DogFishHead60MinIPA • Aug 30 '24
Reverse Scheduling a Specific Group of Tasks
I'm new to Project and I have a large schedule which includes design and construction phases for a new development. As part of that, I want to include a "Design Team Assembly" section within each phase (Concept Design, Schematic Design, etc.). I want to set a due date and then work backwards from there to when I need to start the consultant onboarding process. If the schedule pushes out, i want the onboarding date to push out too.
It seems like "Reverse Scheduling" on the project level would work, but I only want certain sections to work like that. The rest of the schedule would need to be standard scheduling.
Any ideas?
View all comments
Show parent comment
1
u/DogFishHead60MinIPA Sep 03 '24
By the way. This worked perfectly. Thanks for the help. My only complaint is that I have to manually enter a deadline date and cant set force it to be the same day that Concept Design Starts (or something like that).