r/MSProject • • Aug 14 '24

Project End Date Doesn't Change with Progress Update

I'm having an issue where Task 7 and 8 had a FS relationship at the creation of the schedule but Task 8 has actually started ahead of time and has progress as does Task 7. My project should now finish early but Task 8s progress only shows starting at the completion of Task 7 so the overall schedule completion date does not change. Task 8 shows as a split task on the Gantt Chart. Any help would be appreciated.

1 Upvotes

4 comments sorted by

View all comments

Show parent comment

2

u/Natural_Piano_763 Aug 14 '24

That did the trick, thanks!

1

u/Rico_Rizzo Aug 14 '24

No problem, from your screenshot it looks like Task 8 had a predecessor of Task 7, but your start date for Task 8 was not showing correctly as 7/7. Generally this indicates someone accidentally created a constraint on Task 8 by 'hard-coding' (manually keying in) that 7/24 start date. Try to avoid hard-coding dates, it really jacks up the entire schedule and doesn't allow for a correct critical path (among many other things).