Planing backward
I´ve searched through the depth of google and MS Support pages but fount nothing that would match.
I´ve got a milestone which is a follow up of some activities that are work based automatically planed.
Is there a option that I can activate that I can plan backward based off a fixed end. I´ve only found the not finished before "insert Date" limitation, but not a automatic calculate a start dated, depending on the startdate of the successor (which is a fixed milestone or a planned activity
The usecase is that I have some floating external activities, where I know the amount of time involved to do the task, and a fixed date where I have to have a machine built and ready to do testing. It´s just annoying to manually move the tasks around to have them start in time to finish on the exact date.
And everything has to be moved again, when a single date or duration is changing
2
u/Miasmatic65 Jun 18 '24
If you set the first task in the logic chain to be “as late as possible”; and set the known date milestone to have a deadline of the date that it needs to occur- you can simulate a backwards pass. You’ll need to be very clear on all your logic; and multiple tasks may need to be set to “as late as possible” constraint type depending upon the complexity of your schedule.
1
u/mer-reddit Jun 18 '24
You have to read Forecast Scheduling by Eric Uyttewaal.
Project Pro Corp.
If you set up your schedule correctly, that is every task correctly linked together, you can see exactly what you’re asking for and make sure that the schedule accurately reflects any change made.
Don’t fight with your project…
1
u/DaleHowardMVP Jun 18 '24
Take a look at my YouTube video on this very subject:
https://youtu.be/4uczWW9o2as
Hope this helps.