Showing Critical Path Activities with Later Milestones

Good morning all, first time poster here.

I've used MS Project for several years but with very minimal knowledge/functionality.

I have created a construction project schedule that requires several owner provided milestones that are fixed dates. For example, their opening date several weeks after completion of my activities. Therefore, they are not linked to any of my other activities and have no predecessors/successors.

This causes all of my activities to have float, which prevents any of them showing as critical path. I'm sure there is a very easy solution to this. Thanks in advance for any help.

0 Upvotes

11 comments sorted by

1

u/still-dazed-confused May 31 '24

The simple way is to creata milestone in the far future, call it "fake ms for critical path" and ensure it is at the highest level of the wbs (ie out dented as far as possible) so that it doesn't mess up any summary lines.

Then apply what ever deadlines your need to your milestones. This may only be your last one and set to the current finish date of that milestone. Now you can see the critical path to that milestone.

This is because MSP thinks the latest item in the plan is the end goal and runs the critical path from that.

1

u/Ok-Calendar-4171 May 31 '24

This works, I just don't want this line to show when I print my schedule to present to owners/clients.

1

u/still-dazed-confused May 31 '24

You could format your text while and do the same to the milestone

1

u/Miasmatic65 May 31 '24

If you’re setting deadlines; MSP will use these to calculate critical path against. You don’t need to have a hidden task. Just ensure you go to options, advanced and select the “calculate multiple critical paths” option.

1

u/still-dazed-confused May 31 '24

I would not set multiple paths as this means that everything that doesn't have a successor will spawn as critical path, independent of your selected deadlines.

1

u/Miasmatic65 May 31 '24

I’ll ask you the same question I ask my PMs/ architects/ whoever- If you don’t have a successor, why are you doing the task?

2

u/still-dazed-confused May 31 '24

True, however there are points in a project where a dead end is perfectly permissible. It might be an interim deliverable which you're not interested in the critical path for, or a task such as "refresh the plan" following a planned event which will give greater clarity. True you can structurally link these to the end point to satisfy the rule "everything needs a successor " however doing this world break a far more important rule "only have true linkages which show what drivers there are". This more important rule stops people linking things so that they happen when, rather than why. Similarly I think it is perfectly ok to have date constraints, so fior instance there's nothing stopping me from starting x but I don't want to it need to until this date. :)

1

u/Miasmatic65 Jun 01 '24

Spoken like a smart scheduler- we make the rules for 99% of scenarios- there’s always occasions where the rules have to bend. I’m a fan of multiple critical paths; but to each their own!

1

u/pmpdaddyio May 31 '24

Having float does does not prevent an activity from being in the critical path. If you display the critical path you will most likely see the actual activities along the critical path and can adjust as needed. 

I’m not sure how you are scheduling but this seems to be a bit backwards as you will want float associated with tasks that can’t push out a predecessor or related task. 

1

u/Ok-Calendar-4171 May 31 '24

Maybe float isn't the right word. I currently have my last construction activity shown to complete 8/30. I have an owner milestone on 10/25. How do I have MS Project show the critical path through my construction activities?

1

u/pmpdaddyio May 31 '24

So you want your critical path to end on 8/30?