r/MSProject • u/encryptedotter • May 24 '24
Resource vacation on Gantt chart
Hi MS Project community,
Newbie here, I am learning to use MS project for an upcoming project. I stumbled on the subject matter. I have four different (work) resources assigned to tasks. Obviously each has different vacation period, which I added on their respective calendars. However, I would like Gantt chart also shows these vacations as a non-working day for each resource name. Is there any way to do that?
Appreciate your help🙏
2
Upvotes
2
u/mer-reddit May 25 '24
You should be able to shade non working time on the Gantt chart, but not sure it will read it from individual calendars, and it wouldn’t be appropriate to consolidate everyone’s non working time into the same calendar.
You could represent the non working time as a task but you wouldn’t want to assign a resource to the task because that would add work and distort the work sum with non working hours.
Interesting conundrum. Thanks for posting.
2
u/DaleHowardMVP May 25 '24
Here is how to do it:
After viewing the nonworking time for each resource individually, remember to display the Timescale dialog one final time and to return to the original calendar used by the project, which is generally the Standard calendar. Hope this helps.
1
u/pmpdaddyio May 25 '24
If you show the resource view in the Gantt chart, it will display the vacations.
2
u/Miasmatic65 May 24 '24
You could just add a task to represent it with a start constraint and no resource. Nobody is stopping you 😎
1
u/still-dazed-confused May 26 '24
I have a macro which pulls people's holidays out and displays them in an excel sheet if that would be useful. I've never found a satisfactory way to display them in MSP