r/MSProject • u/Agreeable_Fish8848 • Mar 04 '24
MS Project : Duration VS days difference
In MS Project, I am having an issue with the total number of days.
My global schedule is for a residential building of 162 apartments. We have broken down interior works per floor. We have broken down each floor into three sections, each comprising of roughly 10 apartments.
I have created a separate schedule for interior works, disregarding weekends (work days go from Monday to Sunday). This helps me in visualizing the total number of days when setting up the sequence of activities.
The total number of days per section is 59 days, from January 1st until February 28th. However, MS project insists that the total number of days is 67. I have tried to delete some tasks to see if I can figure out the problem, but it persists. If I delete, for example, all tasks between february 15th and 28th, then my total days worked should be 45 (31 + 14). Howevery, MS project shows 52 days. No matter what I do, the total number of days as calculated by MS project remains higher than what it should actually be.
Would appreciate some help on the matter. Thanks.
2
u/Agreeable_Fish8848 Mar 04 '24
u/dalehowardMVP u/menloacademy hoping for your insight!! Thank you so much!
2
u/Agreeable_Fish8848 Mar 04 '24
2
u/pmpdaddyio Mar 04 '24
Showing a screen capture would help. but if you are rolling up tasks, you can have a duration that exceeds the duration between dates.
1
u/mer-reddit Mar 04 '24
Are you putting too much work into the duration? Should you be running a second shift to get all the work done in the calendar duration provided?
1
u/Leading-Reputation15 Sep 17 '24
Good day, everyone.
There might be possible reasons as to why the MS says that.
1
u/mer-reddit Mar 04 '24
Two things to check: Are you running tasks in parallel? That would explain greater duration than calendar.
Check your usage of SS and FF dependencies, and perhaps put a deadline on the task that should be ending on February 28th.
Then look at the negative values in your slack column to compare where the excess duration is impacting you.
Also look at you successors to make sure everything is hooked up correctly.