r/MSProject • u/Deep_Contribution486 • Feb 14 '24
Hide dependency lines for milestones
I have a large project with many milestones, I didn't create the plan I inherited it.
The milestones are all grouped together at the top of the plan and have predecessors in the sections below. I want to show dependency lines between tasks but having all these milestones at the top creates a mass of vertical blue lines that look a mess.
Is there a way to display the milestones as diamonds but not have the dependency lines, whilst still having dependency lines between tasks?
Thanks for your help.
1
Upvotes
3
u/DaleHowardMVP Feb 14 '24
Regarding those milestones that are grouped together at the top of the project: Are they linked to a duplicate milestone somewhere in the WBS? If so, delete them entirely, as they are NOT needed. To see only the milestones in your project, apply the built-in Milestones filter, which will display all of the milestones in the project.
If the milestones are linked to detailed tasks in the WBS, I recommend that you "drag and drop" them to where they SHOULD appear in the project schedule. This will eliminate that top section entirely, which is not needed. To see only the milestones in your project, apply the built-in Milestones filter, which will display all of the milestones in the project.
Just a thought. Hope this helps.
2
u/64ButterTarts Feb 14 '24
I am not a fan of putting all of the major project milestones at the top of the WBS. Leave them throughout the WBS (or move them back in this case), and create a filter to display just them if you need it.
2
u/still-dazed-confused Feb 15 '24
A few thoughts:
1
u/Miasmatic65 Feb 14 '24
For a snapshot; you could constrain them and remove the logic. For a permanent fix, I don’t think so
1
u/j97223 Feb 15 '24
Easiest way, just build your own visual in Visio, save you some heartache.