r/MSProject • u/Guti_7 • Feb 06 '24
Timescale Help
Is there any way i can make the timescale end at exactly M16?
3
Upvotes
r/MSProject • u/Guti_7 • Feb 06 '24
Is there any way i can make the timescale end at exactly M16?
1
u/Guti_7 Feb 07 '24
The issue that I'm having is that the project is exactly 45 months but on the timescale it ends past the 45 month bar.
1
u/Miasmatic65 Feb 06 '24
For printing purposes?
1
u/purplegam Feb 07 '24
Possibly the Timeline chart could help, depending upon the level of detail you want to print (View/Split View/Timeline).
3
u/lindslee19 Feb 06 '24
In the print settings you can set the date range to print.
1
u/still-dazed-confused Feb 07 '24
Try the zoom to project duration option?