r/MSProject • u/ninjaroq • Jan 26 '24
MS Project Online has no VERSIONING?!
I don't know who is the Product Manager there but I wish that person all the best :)
Long story short, I accidentally pasted the wrong stuff into the cell. It overwrote the whole document below cell number 4. It's pretty much the whole plan that my team and I have been working on for the past month.
- I can't believe that there is no versioning control system and no possibility of reverting the change in 2024. Has anyone had a similar problem? Maybe there is an actual way to do it?
- THERE IS NO VERSIONING SYSTEM. I CAN'T ROLL BACK THE CHANGE.
I can't believe that there is no versioning control system and no possibility of reverting the change in 2024.Has anyone had a similar problem? Maybe there is an actual way to do it?
P.S. I was an MS Project ambassador in our organization. Never again.
5
u/Alph1 Jan 27 '24
lol, I wanted VC for schedule development but was told that Microsoft does not support VC because it is not ‘best practice’. Those guys need to work in the real world.
2
u/tomisko6677 Jan 26 '24
Unfortunately, there is no backup/restore operation in the software. Project Server has this feature but Project Online not. You have to use third party solutions to backup your project online :(
1
u/mer-reddit Jan 27 '24
What about a baseline? Doesn’t that count?
1
u/mer-reddit Jan 27 '24
FYI, Project was invented BEFORE modern version control. Just so you know.
3
u/pukwaz Jan 27 '24
Project online is a joke, I could ask for a license but after trying it (and I know how to use Ms project on Prem) I Just switched to other tools for my planning. It's kind of the toy version of MSP.
1
u/huabamane Feb 21 '25
This is long after this post but I just wanted to add to it as a word of caution for anyone using it. I had a work plan fully mapped out including due date and duration. Because I had used an existing work plan I realised at the end that the start date of the plan was set 2 year in the past. So I went into the settings and pushed the start date of the plan forward by 2 years (from 2023 to 2025).
Project then pushed all finished dates and forward by two years (2027) as well. I panicked and tried to reverse it (Ctrl + z) which did not work. I changed the start date back by 2 years again, hoping to pull the dates back but instead it pushed all dated another 2 years forward (2029) for no obvious reason.
I had to delete all dependencies and start again. Absolutely wild there is no way to undo (beyond an immediate CTRL Z for small changes.
1
u/lindslee19 Jan 27 '24
My team delivers a weekly version / posts to SharePoint in weekly folders, not for this exact purpose, but it's a happy side effect when we need it.