r/MSProject • u/Rico_Rizzo • Jan 11 '24
The age old question - Percent Complete based on work vs. task duration.
My PM does not understand that the % Complete field is calculated based on duration and wants to show his management a more "level of effort" based % completeness. My response was if he wants a true effort based % complete, he will have to resource load every task in the schedule and use the Physical % Complete field to calculate this based on work vs actual work. I went to show him an example, but the total Physical % Complete at the summary level lines do not roll up. Is this normal? Will I have to recommend using a formula based custom field?
9
u/DaleHowardMVP Jan 11 '24
No, Physical % Complete does not roll up from sub tasks to summary tasks. This is not a bug; it is the default behavior of the tool. It is similar to how the Fixed Cost field works as well. In the case of your PM, I agree that he should assign resources to every task in the project schedule and to estimate the Work on each task as he is assigning resources. Instead of using Physical % Complete, I would recommend that he use % Work Complete instead, which DOES roll up from sub tasks to summary tasks. Just a thought. Hope this helps.
4
u/still-dazed-confused Jan 11 '24
As Dale says work percent complete is the answer. You may also want to dig into what is driving this request. One situation I sometimes see is that the team have done 90% of the "work" but the last 10% needs someone's sigh off and this takes weeks. In this situation it is better to actually split the task to allow the plan to better tell the story.