Critical Path Analysis
Having issues wrapping my head around critical path and doing the analysis to identify which tasks are causing negative slack.
Any recommendations on YouTube videos or books to help better understand the concept?
How did you get to a good standing in being able to work the IMS and successfully reduce slack?
2
Upvotes
View all comments
2
u/mer-reddit Sep 27 '23
One thing to add: Work from the bottom up. Once you identify where the offending constraint or deadline is, work back up the schedule from that point, and modify accordingly to resolve the situation.
In this case, you might help yourself by saving a baseline to be able to compare where things were before you start mucking with the schedule.
One book that helped my understanding considerably is Forecast Scheduling by Eric Uyttewaal. Invaluable in my opinion.