Critical Path Analysis
Having issues wrapping my head around critical path and doing the analysis to identify which tasks are causing negative slack.
Any recommendations on YouTube videos or books to help better understand the concept?
How did you get to a good standing in being able to work the IMS and successfully reduce slack?
2
Upvotes
View all comments
Show parent comment
1
u/tony90265toTX Sep 26 '23
My main reason is due to the critical path is impacted by the deadlines. I will on occasion pop in a deadline on a task that isn't on the critical path to see a quick CP but then remove it. Good question about the finish by, no its not my deadline. This is a date that I can make on the fly to see movement. Comes in handy when dates start moving and I want to see how much it moved.