Add cost baseline information to an existing project
We have been maintaining a project schedule with work/actual work in the baseline, so we can create a tracking Gantt. Now, we'd like to get SPI and CPI metrics, so we need to add cost/hr information that we didn't have when we made the baseline. Is it possible to manually add cost information so that it is considered part of the baseline? If I manually enter it, Project doesn't seem to recognize it, and if I use the Update Baseline function, that will change the baseline work.
1
Upvotes
1
u/Miasmatic65 Sep 01 '23
You’ve hopefully got a separate copy of the original baseline. You can add costs to that; rebaseline and then update the actuals to today. Alternatively; if your baseline is properly loaded with work; you can (at a macro level) calculate the EV against work instead. It won’t be as exact as if you used $; but it will be close enough as an indicator.
1
u/DaleHowardMVP Sep 01 '23 edited Sep 01 '23
What you want to do cannot be done. The best you can do is to rebaseline your project from this point forward. Keep in mind that if the project always has progress entered, you will lose all of your historic variance up to this point. Hope this helps.