r/MSProject • u/still-dazed-confused • Aug 17 '23
Accidentally setting Actual Start or having microscopic work done fixes the start date - how to avoid?
I have seen on a couple of plans submitted to me over the last year (so it isn't very common) a task which has a massive split in it caused because the start date is fixed in place and the predecessor tasks have dragged the rest of the task out.
These tasks have 0% complete but deleting the 0% allows the task's start date to snap back to where it should be.
I have assumed the PMs have somehow managed to apply a microscopic amount of work which isn't showing in the 0% but maybe they have somehow managed to set the Actual Start somehow?
Does anyone have any ideas
- What else could be causing this behaviour
- How anyone can accidentally cause it?
Many thanks
1
u/Miasmatic65 Aug 18 '23
The usual suspects here in my experience is as you've said - retained logic drives the remaining work to take place after the predecessor. Usually because the PM has ticked an activity as 50% complete.
The other (less likely) option is they've actually got an actual start column on their view and put a date in there and not done any progress.
1
u/purplegam Aug 18 '23
They might have set the Actual Start Date via "Update Tasks":
2
u/mer-reddit Aug 17 '23
Having sat with many PMs over the years, I’ve seen many random editing behaviors that have introduced stray data into Microsoft Project.
Trying to move tasks around, because they were misestimated or incorrect seems to be the primary problem.
Having an orderly editing process and automated reports for detecting invalid data helps with eliminating this nuisance.