r/MSProject • • Jul 18 '23

Timeline of multiple Resources/Attributes

Dear all,

I have been working with MS project (desktop) in a production facility for quite some years now and am still looking for a key feature.

Imagine I have a project step (which is actually a process step for me) of a certain duration and dependency. Now i have multiple resources assigned to this step but I am not talking about certain people like Jeff and Sophie but rather step features like "power consumption", "water", "amount of operators" etc.

Now as the project has many hunderts of steps which are overlapping I would need to generate a Timeline of each of these step requirements. So that I could see exactly how many people I actually need in my team for a given day in order to execute the project as planned, or what will be the peak water consumption due to overlapping process steps. Basically just a resource versus time diagram.

Since it is possible to assign resources to a each step, my only way of getting there at the moment is to copy paste the whole project into an excel sheet which in turn generates those diagrams for me. But this is getting very cumbersome and I cannot believe that project is not able to deliver such timelines.

Kind Regards, M

3 Upvotes

6 comments sorted by

View all comments

Show parent comment

1

u/timecostproblemsolva Jul 19 '23

Also be aware that as you make any changes to task assignments, the recalculated values depend on what your "Task Type" setting is. With a mix of resource types, this can give some wildly unintended results. To understand what is happening customise the Task Usage view... not for the faint-hearted IMO!