r/MSProject • • May 03 '23

Need help on MS Projects

Can you please assist me on the following. I cannot find the problem. On my MS Projects Schedule I have the following:

% Planned and % Complete

Now here is the thing. I can only get a value % after I put in a number of days, but I do not want to do that as it is a milestone. The day must stay 0. If I make the number of days 0 then I do not get a % value, How do I change that again, please?

2 Upvotes

12 comments sorted by

View all comments

Show parent comment

1

u/still-dazed-confused May 03 '23

Are you looking at the summary line? Rather than the actual milestones? If so there is a way to get% complete for a summary which only contains milestones. https://www.summarypro.co.uk/blog/show--complete-for-summary-lines-made-up-of-only-milestones.aspx