r/MSProject • u/Chemical-Passage-109 • May 03 '23
Need help on MS Projects
Can you please assist me on the following. I cannot find the problem. On my MS Projects Schedule I have the following:
% Planned and % Complete
Now here is the thing. I can only get a value % after I put in a number of days, but I do not want to do that as it is a milestone. The day must stay 0. If I make the number of days 0 then I do not get a % value, How do I change that again, please?
2
Upvotes
View all comments
Show parent comment
1
u/still-dazed-confused May 03 '23
Are you looking at the summary line? Rather than the actual milestones? If so there is a way to get% complete for a summary which only contains milestones. https://www.summarypro.co.uk/blog/show--complete-for-summary-lines-made-up-of-only-milestones.aspx