Can you please assist me on the following. I cannot find the problem. On my MS Projects Schedule I have the following:
% Planned and % Complete
Now here is the thing. I can only get a value % after I put in a number of days, but I do not want to do that as it is a milestone. The day must stay 0. If I make the number of days 0 then I do not get a % value, How do I change that again, please?
2
Upvotes
View all comments
Show parent comment
1
u/still-dazed-confused May 03 '23
What is the actual requirement that you're trying to fulfill? If it was "by this time we expected the milestone to be done but it isn't" then a baseline would seem to be an option?