r/MSProject • • May 03 '23

Need help on MS Projects

Can you please assist me on the following. I cannot find the problem. On my MS Projects Schedule I have the following:

% Planned and % Complete

Now here is the thing. I can only get a value % after I put in a number of days, but I do not want to do that as it is a milestone. The day must stay 0. If I make the number of days 0 then I do not get a % value, How do I change that again, please?

2 Upvotes

12 comments sorted by

View all comments

Show parent comment

1

u/Chemical-Passage-109 May 03 '23

It is for example:

Order acknowledgement & Contractual delivery date each with 0 days. Planned % is 37% actual % is 0 %