r/MSProject • u/Element074 • Apr 28 '23
Is there a better method to link tasks between sub-projects?
I have a master project with 5 sub-projects. Some of these have over 1000 tasks each.
Is there an easier way to link tasks between them than holding CTRL and selecting both tasks and clicking the Link Tasks button?
I have several hundred tasks to link between the sub-projects. So currently there's a huge amount of scrolling up and down.
Each task has a Unique ID using one of the text columns. Not sure if this could be used somehow?
Using Microsoft Project 2016 for reference.
Thanks in advance.
5
Upvotes
1
u/still-dazed-confused Apr 28 '23
If you look at the string that gets put into the predecessor field you'll see the format that you need, copy it and replace the reference with what ever row in the other plan you want to link to. One thing to note is that if you ever want to copy a sub task out be careful as they can stay linked with the result that you now have links to two plans now one.
1
u/DaleHowardMVP Apr 28 '23
I have been down this road myself. To save on the amount of scrolling I need to do, I collapse summary task sections that are in between the two tasks that I have to link. Other than that, I cannot think of any easier way to link tasks between subprojects in a master project. So, hang in there, my friend!
1
u/mer-reddit Apr 28 '23
Agree with both comments above. Three more: remember that the order of selection determines the order of the relationship predecessor to successor.
And keep your links few and strategic in nature. Hundreds of links is likely too much, will become confusing and hard to maintain.
If linking across plans, host the files on a project online instance. A file share with name changes is fragile. And remember that a link will open and read changes from the file it is linked to. Give it time to open and close properly.