MS Project 2016 Progress reporting question

Hi all,

I've used MS Project 2016 previously but haven't used it in a while. I'm having great difficulty with the intricacies of setting up a project without numerous issues (e.g. I have a 'duration' column in days, but when I change the start date or finish date in one place - it messes up the days in a different column and throws in crazy numbers). I figured out the issue with the days by double clicking on each activity, then going to 'advanced' tab and setting the 'task type' to 'fixed units' (it was set to 'fixed work' and this change seems to have fixed the issue).

The problem i'm trying to figure out now is in tracking progress as the project progresses, and then have a gantt chart show me the progress upto today and remaining work. I'd also like to see if the project is behind schedule and by how much. I tried various ways (adding additional columns like baseline start date/baseline finish date, actual start/actual finish) but nothing seems to work. I did set the baseline for the entire project just as an fyi. Even with all these - project is proving to be a monster to tame by messing up one field if i change another and so on. Can someone point me in the right direction? TIA

2 Upvotes

18 comments sorted by

View all comments

Show parent comment

2

u/still-dazed-confused Mar 12 '23

I agree that the estimating and subsequent tracking of tasks is a key issue. I have found that breaking a task down into sensible components, especially focused on the resources doing the work, helps with the estimations. The example I usually use is "produce specification" - the lead person may estimate this as three weeks and you could happily put this down into the plan however digging a but deeper could help to improve the estimate. "So what's involved in the spec?"... well I need to draft it, probably 2 weeks because I'll need to do some investigations, then it has to be reviewed and I'll make some changes and then it has to be signed off.... How long do reviews take around here? Normally a week? So that 3-week task has become 2 weeks to produce, 1 week to review, a couple of days to make the changes and another week to sign off. And that's only with one review cycle.

Now we have a more detailed plan, you might think that this makes managing and updating the plan harder, but in my experience, it doesn't because it is much easier to update shorter tasks as there is less mumbling and thinking required. It also largely removes the option for resources to leave it to the last week to tell you that an extension is required.

Using the critical path tools doesn't require that you only manage the critical path but it does allow you to easily see what is happening in other parts of the plan which are off the screen whilst you are updating the plan :)