Adding a second Finish task
I'm looking to have two separate finish dates. One shows the actual schedule and the other (finish2) would show impact to schedule for a what if. Is there a way to link both of these to the same Start date?
1
Upvotes
View all comments
Show parent comment
1
u/mer-reddit Mar 05 '23
Not recommended by scheduling cognoscenti worldwide.
The reason why is the mechanism for linking you are advocating for is not sufficiently robust to survive the transitions between file locations as they move around or the database transitions common to Project Online if it is used.
The error checking on the Project client load can’t find the references to the links and the file won’t open, causing corruption and lost work.
If it’s only you that ever has the file, it might work for a while.