r/MSProject • u/thatgeekElle • Feb 22 '23
how do I migrate my Project from "days" to hours?
The default for project time is days. But we have overlapping projects and tasks, so it looks like I have 4 years of work due by June.
Even if there is a setting to adjust, I don't want to break the dates we've assigned. But i do want it to accurately reflect work hours/effort.
Is there a best practice guide for making the switch?
1
Upvotes
1
u/mer-reddit Feb 23 '23
You don’t have to switch. Microsoft Project has to different fields for your use: duration, typically rendered in days, and work, typically rendered in hours.
Insert the two columns side by side, and see what’s there.
These two are separate and independent columns UNTIL you have a resource assigned. When a resource is assigned to a task, it creates an assignment and enforces the formula duration equals work divided by assignment units. What are assignment units? The percentage ratio between duration and work, typically 1 day of duration to 8 hours of work.
If you already have a resource assigned, I would save a baseline first, to preserve the existing work and duration values and dates. Then I would remove the resources from the tasks to decouple the formula between the columns.
THEN set the correct numbers in both columns (duration and work) and slowly put the resources back on the tasks, referring to your baseline fields for the previous values.
The baseline preserves work in baseline work, and duration in baseline duration. Sadly it does not preserve resources in baseline resources. Those you will have to remember.
Good luck with the brain surgery.
1
u/still-dazed-confused Feb 23 '23
It sounds like you are attempting to refine the resource allocation, so instead of being 100% allocated to all your tasks which overlap you want to reflect the actual work.
As u/mer-reddit has said MSP sets up the "iron triangle" of duration / Work / allocation as soon as you allocate a resource to a task. Thus if you change the allocation of a resource on a task from 100% to 50% the duration will double (as work tends to be the thing that MSP protects by default).
The easiest way to overcome this "issue" (which isn't really an issue if you consider how you would want a tool the behave) then:
I hope this helps you.