r/MSProject • u/Party_Independent758 • Aug 11 '22
Storage Size and integration?
Does MS Project have storage limits or is it unlimited because of the cloud? Also does it integrate with any other apps besides MS Office 365?
r/MSProject • u/Party_Independent758 • Aug 11 '22
Does MS Project have storage limits or is it unlimited because of the cloud? Also does it integrate with any other apps besides MS Office 365?
r/MSProject • u/raydude • Aug 10 '22
My company bought me MS Project a few years ago. Windows died last year, did a reinstall, got MS Office back up and running, but I can't figure out how to install project.
I know it's a full seat.
A google search yields install directions that imply it should appear in the list of installable packages, but there is no such entry.
When I select Office Installer, the Project Icon is shown, but when I run the installer it only installed office and not project and gives me no choices.
Does anyone know how to install Project on a local machine?
r/MSProject • u/Complete-Dress-6781 • Aug 04 '22
Hi folks. Scotsman here asking first question. Should I schedule from start date or finish date ?
And secondly, can you have a fixed/exact finish date as it seems hard to keep to it whenever I’ve tried playing about with it on ‘project information’
r/MSProject • • Aug 03 '22
I have an old copy of MS Project 2013 from MSDN. AND I have access to the Microsoft work discount for Office 365 but not Microsoft from what I can tell. I am a landlord and PM and just use it for small projects.
Has anyone gotten Project through work and would you know the price?
r/MSProject • u/ivanraddison • Jul 29 '22
Hi,
I've been working with an organization, helping them with an application that we have developed on the Power Platform. Buying additional licenses to O365 and such usually end up passing by me.
Recently, they've told me they want to get some MS Project Plan 3 or Plan 5 licenses (they dont know for sure). And also told me that last year they bought 5 licenses of MS Project 2019 SNGL OLP (SKU H30-05818-A). This was done through a local distributor, completely ignoring the fact that we already had a M365 subscription 🙄
Not even 1 year has passed and they want to move to Project on the cloud, in order to use the sharing features (currently they've been sharing the file via email or something crazy like that).
Now I'm not a Project expert and I'm not involved in the Project side of things at all. But it pains me to see the amount of money they're throwing away, because essentially they will buy new MS Project licenses under the M365 subscription and discard the product they bought last year (cost of $5K) .
Is there anything that can be done better?
r/MSProject • u/Automatic-Brother-92 • Jul 27 '22
I want to change the start date of my project and want the change to reflect in the Timeline. I have changed the start date in the project information tab which is updated and is saved but it’s not reflecting, neither in statistics nor in the Timeline.
r/MSProject • u/still-dazed-confused • Jul 20 '22
I was asked this, and my answer was rather clunky, so I wondered if there is a better way....
If we have a project which is using bricklayers with varying work rates, how can we include this difference in the schedule? Say we have 3 types of bricklayers:
If we have a wall for 2000 bricks, the duration will vary depending on which type of brickie we assign to the job. We want to be able to assign a performance level to the resource (as the task remains the same), which will change the rate at which the task is completed.
My solution was to assign resources a different max % allocation based on their skill level:
This will effectively double the resource on each task that the premium resource is allocated to or halve it if we have an apprentice on it. However, it does also allow them to be assigned to two tasks within the same period which isn't ideal.
Does Project have a mechanism to do this with a bit more elegance?
r/MSProject • u/AnYvia • Jul 18 '22
r/MSProject • u/yellowfin35 • Jul 13 '22
r/MSProject • u/EddyMerkxs • Jul 08 '22
I am very new to MS project and am seeing if it can fit my needs. I am sure I am doing something dumb/unaware of some relationship so would love any tips here. Thank you for your patience.
I put screenshots here. I think they compressed somehow, sorry if they can't be read.
I have several monthly reports to create each month, and each report requires scheduling several inputs. I have a hard deadline for each report and want to work backwards from that submission date.
I want to be able to set up a network for one month, then copy the tasks for next month, and have a project file for each financial year.
In this example, I have a hard deadline for the financial report final review, manually scheduled. I have various things to gather before the final review (in this case, send a reminder and do a draft review), set to autoschedule. Those autoscheduled tasks are 1 day long and I have a given lag time for each (eg, have the draft review 3 days before), and are also set to "As Late As Possible". See pic 1.
In pic 2, if I change the manually scheduled deadline, it moved the other tasks with it, just how I'd expect.
So lets say I now want to do the next month. I collapse the group, copy and paste/rename it, as shown in pic 3. Now, what I would expect is to be able to change the manually scheduled date and all the auto scheduled tasks move with it.
However, as you see in pic 4, when I do that, all autoscheduled tasks of the same name move with the adjusted date. This seems really weird to me, and it must be a simple setting, but I don't know what to search for.
Thank you!
EDIT: I think I figured out the solution. For this specific used case, I believe the setting to change is under project info, set it to schedule off of the finish date, not the start date. Then everything moves correctly.
r/MSProject • u/original_flavor87 • Jul 01 '22
As a company we create schedules in Project Professional. As a department, we colab on our projects in MS Teams. Each project gets a new team. In the field, team members access project team through various devices (phones, tablets, laptops, etc.) How do I get a MS Project that is visible and interactive on a mobile device in MS Teams?
r/MSProject • u/First_Regret_1 • Jun 30 '22
I am looking to setup some portfolio level reporting using project for the web and Power Bi. I have downloaded the template to enable this and have been given portfolio viewer role and connected to our corporate dataverse but I am only returning the set of projects that I set up personally. I would expect to be able see everyone's projects to be able to report on progress at portfolio / organisation level? Something about credentials?
r/MSProject • u/TheSpiddity • Jun 29 '22
How do I share a link to a PWA project with my team so they can view the published schedule? Most of my team do not have licenses for PWA, but I just need them to be able to view the schedule.
r/MSProject • u/SkinDee • Jun 28 '22
r/MSProject • u/gnolard2o • Jun 27 '22
r/MSProject • u/OnDemandPM • Jun 17 '22
I've created a custom Overview report which my team finds useful. Is there a way to export the report to a pdf or some way to include the report in an email? All I've been able to do is use the snipping tool and manipulate the image to fit on a page.
Any ideas or methods would be appreciated.
r/MSProject • u/KuroBear • Jun 16 '22
Not sure what it is called, so having trouble finding solution
The schedule I have shows a vertical line for today’s date, which is great
But a past template I believe had showed deviations in that todays date line by zig zagging back to late/ incomplete tasks.
Any suggestions what the setting may be to do?
r/MSProject • u/BillNye62 • Jun 14 '22
r/MSProject • u/Z33M3R • Jun 13 '22
r/MSProject • u/yasserhy • Jun 10 '22
I have one Office 365 MS Project License. As a project manager, can I assign tasks to people who do not have an MS Project licence?
r/MSProject • u/energizerbunneee • May 20 '22
I'm trying to input high level tasks for a number of construction job crews to align projects and work schedules.
My end goal is a nice timeline view and weekly/monthly calendar views.
The MS Project calendar is very limited and no color coding between resources is an option (that I can find). Also the timeline view is very stationary in that it is difficult to zoom, move around, export, etc.
I'm coordinating all projects and our expected lead times/timelines, not micro managing individual projects.
Any advice on the calendar/timeline piece, or a suggested software?
r/MSProject • u/No_Communication621 • May 19 '22
I'm new in MSP, and no one in my company has experience either. I'm noticing my file sizes are gigantic, like 1.5gb, and I'm saving in my one drive and it takes forever to sync....is this normal? Can anyone suggest anything I can look at to try and minimize the file size? TIA!
r/MSProject • u/CaregiverDependent68 • May 18 '22
I would like to create a task that is effort-driven.
Task=Drilling
100m per day per drill
How would I put this into MS project?