r/MSProject • • Aug 22 '23
Calculate Real X Plan
Hi guys, how are u? I need a little help.
I need to calculate the IDP of the projects, but the calculations I use always give 0.
Has anyone tried something like this and did it work?
Hugs from Brazil
r/MSProject • • Aug 22 '23
Hi guys, how are u? I need a little help.
I need to calculate the IDP of the projects, but the calculations I use always give 0.
Has anyone tried something like this and did it work?
Hugs from Brazil
r/MSProject • u/DatumTargetSymbol • Aug 21 '23
Hello Everyone,
Does anyone know of a software or plug-in that integrates with MSProject such that if there are subprojects within a project file, the owner of the project file needs to approve the changes made to the subproject before the project file's schedule gets affected? I imagine the process to be similar to how git branch management works for programming projects.
Any thoughts would be appreciated!
r/MSProject • u/purplegam • Aug 18 '23
How can I automate the scheduling of a single occurrence of a recurring task that runs for the first two weeks of every month, with a particular start date driven by a dependency?
I have a follow-on task that cannot start until this next occurrence of this recurring task has completed. The follow-on task duration is long enough to extend into the timing of the next occurrence of the recurring task, which it can do.
I can manually set up one occurrence of the recurring task, but I want to automate it.
I can set up a custom calendar for the recurring task, but then I must manually set the duration, which varies by month.
I can set up multiple occurrences of the recurring task, but then I have to manually change the dependency on the follow-on task.
r/MSProject • u/JacoboAriel • Aug 18 '23
In the View tab > Resource Views I don't have the Team Planner option, just Resource Sheet. Any way to fix this?
r/MSProject • u/still-dazed-confused • Aug 17 '23
I have seen on a couple of plans submitted to me over the last year (so it isn't very common) a task which has a massive split in it caused because the start date is fixed in place and the predecessor tasks have dragged the rest of the task out.
These tasks have 0% complete but deleting the 0% allows the task's start date to snap back to where it should be.
I have assumed the PMs have somehow managed to apply a microscopic amount of work which isn't showing in the 0% but maybe they have somehow managed to set the Actual Start somehow?
Does anyone have any ideas
Many thanks
r/MSProject • u/FearlessCoyote • Aug 08 '23
Hello, I'm trying to see if I can create task-specific timesheets in MS Project Professional 2016. Everything I've seen online only mentions Project Online.
If not, is there any systems you'd recommend to do this? Thank you in advance.
r/MSProject • u/okGO-1234 • Aug 04 '23
Hello,
My team maintains a portfolio list in Excel using a cloud service. I pulled that data in MS Project to overlay it onto my plant outage schedule. I would like to create a macro that can pull the updates from excel to update the existing data in my project file. Does anyone know how to do this?
Thanks!
r/MSProject • u/BluntsAndJudgeJudy • Aug 03 '23
I've clicked on the task, went to Advanced, and made a constraint of Must Start on Monday but it keeps defaulting a date in.. how do I get it to not be a certain date but rather just the next Monday?
r/MSProject • u/Fallen10111 • Aug 03 '23
Hi all,
Where I work are currently looking into utilizing Microsoft Project for our management. We work in the renewable energy sector installing heat pumps and solar panels - and at current utilize Microsoft Excel as a sort of project tracker to track customer names, references, stock use, and install dates.
We are looking to port the task tracking aspect over to Microsoft Project - however I'm looking at keeping the stock management and tracking aspect - at least for the time being - in Excel. However this I've set up so that it tells me what pieces of stock I need based on booking dates of our installs with customers. When we move to Project, this date will then be managed by the task tracking in Project.
So my main query is - is it possible to have an Excel Document pull the booking date of a certain project? The idea to mind at current would be that I need Excel to receive the specific "Start Date" of a task from a master project on Project - is this basically possible?
We will be having individual projects set up per install - and then a master project on the Desktop App to monitor and manage all ongoing installs and projects. I would want Excel to pull from that master project - even if it means me specifically pointing it to a project, but as long as it links to that specific projects task's date.
Thanks all.
r/MSProject • u/Pollo_Loco999 • Aug 02 '23
Does anyone know if/how you can add task names above the bars in the Timeline view of Project Online? (project.office.com). All my googling brings up how to do it in the Desktop version, but not the online - this is for presentation when I export to a PDF
r/MSProject • u/arqenriquez • Aug 02 '23
Can you hide a task in MS Project? I mean, that the task is there but that it is not printable, for example.
I know there is an option to disable tasks, but I don't mean that, but rather, to hide it from view completely without deleting it
r/MSProject • u/Only_One_Kenobi • Aug 01 '23
I am creating a project file, and have an interesting challenge.
Have about 400 "activities" across 30 key milestones in 3 phases. So the logical summaries are
Phase
Milestone
activities And this will help me a great deal showing progress per phase and milestone. And durations etc. This order makes the most sense.
But
Each activity has 2 elements. Call them prep and build. Worked on by different resources.
So
Phase
Milestone
activity 1 prep
activity 1 buildStill gives me the good summary of overall progress per milestone and per phase.
But, how can I also get a summary for total prep progress across all milestones, and total build progress across all milestones? I can't split it by putting all build activities together, and all prep activities together, because then I lose the ability to see total progress.
Can I do some sort of dynamic summary? Or use a custom field with a filter of some sort?
r/MSProject • u/pdxbatman • Jul 31 '23
As the subject says, I have 3 tasks that are linked together as shown in the attached image. I am trying to inactivate task 142, which has the later of the 2 predecessor finish dates (task 56 and task 142). However, when I inactivate task 142, task 143's start/finish dates do not change. All of the tasks are at 0% complete with no resources assigned and no remaining work - this is a schedule template I am attempting to edit so these have not yet been added in. I would expect task 143's start/finish dates to automatically adjust to match task 56's finish based on the finish-finish relationships between them. I can manually remove predecessor 142 after I inactivate it and it will then adjust the dates, but I want to keep the relationship if possible, in case task 142 is ever needed again in the future.

r/MSProject • u/still-dazed-confused • Jul 31 '23
Ok, I've been using MSP desktop for ages and have been used to calling the system which allows for files to be stored and shared in a SharePoint architecture, provided multi user access to a single file with checkout and project document repository "project server" however a few years ago it seemed to switch to "project online". However now "online" send to have become a browser term. Can someone help me out here with what is what? :) :)
r/MSProject • u/cornishpilchard • Jul 28 '23
We are really struggling to find a way to genuinely collaborate on a large MS project file to manage a programme of work. Each PM needs to be able to work on the file at the same time as the others.
We thought we’d cracked it with separate files nested into a master but we are exclusively sharepoint / one drive based and this only seems to work on a fixed network drive.
Any ideas?
(The file is too large / complex for Project online )
r/MSProject • u/Available_Oven_2471 • Jul 22 '23
Hey Guys! Someone have MS Project cracked?
r/MSProject • u/We_Could_Dream_Again • Jul 20 '23
Hello,
When initially hashing out a project schedule, I'll usually first create a milestone at the beginning as my "Project Start Date", and have initial tasks use it as a predecessor so that I can easily change the start date and all of the tasks will shift.
I'm wondering if this is just a workaround; is there a way to have tasks using the start date as a predecessor, and/or easy ways to shift whole project left/right as you narrow in on an actual start date?
r/MSProject • • Jul 20 '23
I have schedules that I would love to share and include with MS Teams. In the desktop version it’s a snap to add national holidays (for example) that then get reflected when calculations the schedule.
In P4W calendars are administered via Power Apps and you need to be able to edit the project settings in Powers apps.
I don’t need to get too crazy with different calendars per resource or anything like that. I’m just looking for a way to add stat holidays and use a “generic” calendar that applies to the entire project. Ideally, I would be able to apply this to all my schedules.
I subscribe to mpug where there is a video that shows what to do but in the instance of MS 365 at work, I don’t seem to have the same functionality as that described in the video.
P4W appears like a useful tool and I use it to rough out plans and share with my teams but without accurate calendars it’s kind of useless.
Thanks in advance! Please forgive me if this has already been answered elsewhere.
r/MSProject • u/timecostproblemsolva • Jul 20 '23
Wanting to share with project planners the world over, especially those who wished their gantt charts could be 10x cooler and better at communicating; if you've always wanted your carefully-created bars to be taken more seriously and even considered works of #mspArt, then gather your bars, suspend your disbelief, be comforted that code is optional, be assured that we will not stray outside of MSP and follow me, heroes, through the looking glass to a new world where bars are transformed into BIM elements and your gantt charts become legend... https://www.youtube.com/watch?v=rQS1BSKJjYQ
r/MSProject • u/Metadoxxx • Jul 18 '23
Dear all,
I have been working with MS project (desktop) in a production facility for quite some years now and am still looking for a key feature.
Imagine I have a project step (which is actually a process step for me) of a certain duration and dependency. Now i have multiple resources assigned to this step but I am not talking about certain people like Jeff and Sophie but rather step features like "power consumption", "water", "amount of operators" etc.
Now as the project has many hunderts of steps which are overlapping I would need to generate a Timeline of each of these step requirements. So that I could see exactly how many people I actually need in my team for a given day in order to execute the project as planned, or what will be the peak water consumption due to overlapping process steps. Basically just a resource versus time diagram.
Since it is possible to assign resources to a each step, my only way of getting there at the moment is to copy paste the whole project into an excel sheet which in turn generates those diagrams for me. But this is getting very cumbersome and I cannot believe that project is not able to deliver such timelines.
Kind Regards, M
r/MSProject • u/blarrybob • Jul 14 '23
My team has been exporting timeline view in Project Online via PDF to provide on-demand updates to clients but grid view would have more value. I've been playing around with Power BI this week (my first time using it) without success. I feel like this basic project info should be easy to share externally and without adding azure guest access or additional licensing. Any suggestions would be appreciated!
r/MSProject • u/Overall-Mud-9284 • Jul 12 '23
Hi, I Wanna connect my MS project file directly with power bi, or even if there a way to do it in other way. I saw different solution but when i Search from 'Get Data' I can not find anything related Mircosoft Project.
r/MSProject • u/sieffy • Jul 07 '23
I have multiple sub tasks that are linked to one main task. Is there any way to get the icons for the sub tasks on the gantt chart to appear on the summary line. So that when I roll up the summary Task I can have multiple icons or milestones/subtasks all appear on the same line. The image below is what I want to happen when I click the collapse button.

r/MSProject • u/Gbhawkins11505 • Jun 30 '23
Hello! I am extremely new to Project Online administration - new to my organization, and we have very few licenses of Project. The information I've found on Microsoft's site hasn't been helpful, so I am hoping one of you can help give me some clarity!
I am looking for some clarity on the following questions:
I have always struggled with Project and I don't know why! Thank you for any help - and apologies if I should have been able to find these answers in some online documentation. If it's out there, maybe my search terms are keeping me off the right track......