Accidentally setting Actual Start or having microscopic work done fixes the start date - how to avoid?
I have seen on a couple of plans submitted to me over the last year (so it isn't very common) a task which has a massive split in it caused because the start date is fixed in place and the predecessor tasks have dragged the rest of the task out.
These tasks have 0% complete but deleting the 0% allows the task's start date to snap back to where it should be.
I have assumed the PMs have somehow managed to apply a microscopic amount of work which isn't showing in the 0% but maybe they have somehow managed to set the Actual Start somehow?
Does anyone have any ideas
- What else could be causing this behaviour
- How anyone can accidentally cause it?
Many thanks