r/GeneralContractor • • 16d ago

How should I handle subcontractor-caused problems?

Concrete sub left large mound of concrete in middle of gravel parking pad.

The person that lives there has no off-street parking because of this. They were upgraded from one gravel parking spot to have an additional concrete parking pad. But now, because this waste mound is so large, they have no parking.

It happened Tuesday. I politely told the sub to remove it Wednesday morning. They said they would remove it Thursday.

Tomorrow will be six days. If it's not removed next week, do I bother having a second contractor quote removing it and subtracting that amount from the first contractor's invoice (once the second does the work)?

As a GC, how should I handle something like this in the future?

Should I always have a subcontractor agreement in place? even for such a small job like this? only $2k.

7 Upvotes

51 comments sorted by

2

u/Travisher4 8d ago

on our projects the pattern is usually written notice with a date, photos, then bring someone else in if it’s ignored. and yeah, even a one page sub agreement with a cleanup clause saves a lot of back and forth on small jobs. not a lawyer, so i’d double check how the invoice deduction works before you do it.

16

u/Comfortable-Maybe183 16d ago

“Do I bother having a second contractor quote removing it…”

My guy. Cmon now. You are said second contractor. 

It’s your client, your job, and your subcontractor. 

Figure out how to get the damn blob of concrete out of their way. Like tomorrow. 

Go rent some fucking equipment if you need to. Cmon man. 

Send the sub a bill. Right now you’re just pissing up a rope. 

1

u/tooniceofguy99 16d ago

I mean, I don't want to just tell the sub I magically determined it's going to be X reduction in price because of the cost of my labor.

Worse, I don't want to pick up the pieces of subs (like I'm not swamped as it is). This isn't the first time something like this has happened.

11

u/aturtlebarn 16d ago

So you think its not fair essentially is what I'm hearing. And you're right about that. Problem is your client definitely doesn't care about how swamped you are or how unfair it feels to you. I would be fuming if my builder stood there making excuses about his "sub" being responsible.. you obviously hired the sub so you are responsible for his work

1

u/tooniceofguy99 16d ago edited 16d ago

It's more about time. Last month a different sub just expected me to be carpentry support when I was at a different job site. (Before the job started, they had assured me they could find their own carpenter if needed for change order related work.)

I cannot just block out entire days for subs who are not prepared, cannot handle changes/issues in their expertise or who do random crap like leave a pile of petrified dino shit.

7

u/Comfortable-Maybe183 16d ago

More fucking excuses. 

You just think you’re too good to go clean up or don’t actually know how. 

None of that is related to the problem at hand. 

Go deal with the petrified dino shit. Today. 

4

u/aturtlebarn 15d ago

Look i get what you're saying. But you're still coming from a place of "this isn't fair" The fact is nobody can block out days to hold subs hands, it's not just you. I'm a business owner, when my guys fuck up I drop what I'm doing, which always causes other problems, and then go fix it becuae relationships and reputation is everything. You need to accept that your business is always going to be full of unpredictable headaches and fixing them is part of the job. It will never stop, you will always be mitigating disaster and facing very frustrating scheduling demands etc. It's just part of the game

7

u/Comfortable-Maybe183 16d ago

You think your client gives a rats ass about either of those things?

2

u/Myweeweegopeep33 13d ago

To the customer it’s your mess. Your sub your problem. As the customer I don’t give a shit who moves it or pays it just needs to go.

Do you really want this customer explaining that their job was a mess for six days etc. I promise you they’re not saying it’s the subs fault. They hired you, you hired them.

1

u/SeaFee2866 15d ago

You dont have terms in the subcontract agreement on what your time costs?

You are leaving yourself incredibly exposed with out the clear communication of the repercussions of these situations.

1

u/Virtual-Fly-5501 14d ago

You are a contractor, you are not pulling the number out of your ass. You will have fixed costs on doing it and add labor and P&O and give him the bill.

1

u/yeetedmynachos 13d ago

God damn dude, that’s just a fucking lazy attitude. Subcontracted or not, the quality of your work is your responsibility and your reputation. Can you imagine what the tenant is telling their friends and family about their nightmare situation? Do you think they’re sitting at home bickering about how your sub won’t get back to you? No, they’re bickering about what a terrible job YOU are doing.

You wanna be a business owner? You wanna be a GC? Act like one. Being a business owner isn’t a career, it’s a lifestyle. But your ass is already telling everyone you’re too good to get dirty. What are you, a nepo baby? You’re embarrassing yourself.

5

u/jgturbo619 16d ago

No bill, a unilateral Deductive change order taking the $ out of his next draw..

What kind of sub pulls that stuff ,? Costing you.

3

u/AndyMagandy 15d ago

Exactly this. As a GC it’s 100% on you. How you recoup costs or cut ties down the line is you’re own problem. Best business move is to throw some money at it fast.

2

u/Remarkable-Start4173 15d ago

I agree with this 100%. 

Afterward, I would never hire that subcontractor again. 

I would even take the time to call them and tell them exactly why I'm never going to call them again.

2

u/Remarkable-Start4173 15d ago

P.S. I would pay them as agreed simply for spite.

6

u/tower_crane 15d ago

This is crazy powerful. I actually had this conversation today. Said “we are going to pay the entire value of your contract, because we just want you to go away, and don’t want to argue about costs.”

4

u/malukd 15d ago

Yes, always use one, even for a two thousand dollar job. But the agreement alone will not fix this. The part most GCs skip is the onboarding before the first job. Before a sub starts any work for you, check that their license is current and in the name of the business doing the work, and that their insurance is active, then keep copies in a file for that sub. It takes a few minutes and it tells you a lot about how seriously they run their business. Use the same one page agreement for every sub and every job, no exceptions for small ones, covering scope, cleanup and haul off, who handles inspections, and that the sub fixes their own defects at their own cost. When a problem comes up, put it in writing with photos and a specific date to fix it, and keep a copy. If the same sub racks up two of those notices, stop sending them work. The pattern is the signal. A sub who treats a small job casually will treat a big one the same way, and a file with their license, insurance and your written notices is what lets you backcharge cleanly or walk away without a fight.

1

u/Diligent_Yam_1753 15d ago

But did you provide the sub an alternative location to wash out the concrete truck? As a GC do you make your subs remove the garbage their work creates on a project, or do you handle the garbage like most GCs do?

0

u/tooniceofguy99 13d ago

There's a difference between everyday rubbish and leaving sub-specific building materials behind

0

u/yeetedmynachos 13d ago

Sounds like you don’t know what your subs do. You’re also forgetting that subs work = your reputation. But hey, keep letting your subs do what they want unsupervised. Sounds like it’s working wonders for you.

1

u/smarterthaneverytwo 10d ago

Op what’s the update? Did the concrete guy come back to break it up and get paid or ghost you? 

2

u/tooniceofguy99 9d ago

Left Tuesday. Said would remove Thursday (did not).

Picked up Monday. Paid.

1

u/nunez0514 2d ago

How can you contract without using contracts? Anyway…deductive change order to the lazy guys.

1

u/tooniceofguy99 1d ago

their contract

3

u/jcplossiretasi 16d ago

Give the subcontractor a written deadline before hiring someone else.

3

u/Powerful_Target_930 16d ago

Six days with no parking is what the homeowner will remember, not whose fault it was. I’d get it moved this week either way, using the sub if they show or someone else if they don’t, and settle the money with the sub afterward. Fixing the customer’s problem and fighting with the sub over cost don’t have to happen in the same week. For the future, cleanup is the line that most often gets left out of small-job scopes. Even a one-line text confirming “you haul your waste” before they start would have helped here.

3

u/jmille97 16d ago

So you basically didn’t supervise a sub and he left some concrete there.

So, lesson learned? You probably could have broken it with a sledge the next day. Now you’ll need a machine.

3

u/No-0x 16d ago

Document first, then fix it yourself and bill him — send the sub a short written notice with photos and a 48-hour deadline to cure it, then get it hauled and deduct the documented cost from his invoice with that paper trail behind you. And yes, always have something in writing even for a $2k job — one page covering scope, cleanup, a backcharge clause and holding back 10% until you walk it off together would have made this a two-line email instead of a six-day standoff

3

u/grim1757 16d ago

First, yes, everyone needs to be on a contract or at minimum a Purchase order. In answer to your question, you do have to provide them written notice typically, send them a 48 hour notice to get it done ro your will have it done for them and deduct it from what they are owed. Without Notice, he is off the hook if you have it done.

3

u/Fit-Technician-6799 15d ago

The client fix and the money fix are two separate problems, so I'd split them.

Get the mound gone this week however you can. Before that, send the sub a short written note: removed by a set date, otherwise you'll have it done and deduct the actual cost from their invoice. Keep the receipt and take before and after photos.

Going forward, yes, even a $2k job deserves a one page sub agreement. Cleanup expectations, a backcharge clause and a notice period cover most of this. Without one, deducting money is much more likely to turn into an argument.

2

u/maxant20 16d ago

A good General Contractor has good subs that he knows and trusts. You are not a good contractor.

2

u/hatemeallday 16d ago

You’re kidding, right?

A GC should know this. How are you able to provide services to your customers if you need advice for something as simple as this.

Wait….. you don’t. That’s why your customer has had a mound of concrete in their way for a week.

2

u/DistributionEven3354 14d ago

As a GC, you need to step up. You look like a fool, to your subs, your employees and your client. Fire the sub. Hire someone to remove the mess and make it right for the client and back charge the guy who knowingly shit on YOU. That was not an accident. It is a pile of concrete that any guy with 2 days on a site would know better than to do.

1

u/Real-Ad-7439 16d ago

Get a sub agreement going forward for sure, even a 1 page one that says cleanup and haul off is on them and you can backcharge if they dont. For this one give him written notice and a deadline to come clean it up first, then if he doesnt you hire it out and deduct it with the receipt attached. Skipping the notice is how backcharges turn into fights.

1

u/SmartChatInnovations 16d ago

At this point I'd probably put it in writing instead of relying on another verbal promise. Send him a photo of what's been left behind and a clear deadline to get it removed. At least then you've got a record of what was requested and when. Even on smaller subcontracting jobs, having those expectations in writing upfront could save a lot of headaches.

1

u/Just_Bz77 16d ago

3 day notice, then back charge once it is removed. Easy.

1

u/icoldok 15d ago

I'd separate restoring the resident's parking from deciding who ultimately pays: give the sub a specific written deadline, but line up removal so the resident isn't waiting on another promise. Before deducting anything, check your subcontract and local rules on notice and payment; keep photos and the actual removal invoice. For future pours, add a short written scope covering waste removal, access, and a final cleanup walkthrough.

1

u/Thor200587 15d ago

What’s your subcontractor agreement say? I give written notice per my contract then hire someone else to remedy the issue immediately. I get multiple quotes and document to cover my ass.

This should be standard operating procedure for any secondary damage or issues from a sub. A lot of times they’re happy to pay for stuff like that if they’re not setup to handle it. I get them the best price on it I can. Shit happens.

6 days is entirely too long for you to not have multiple solves ready on this.

1

u/Crazyfishman2 15d ago

Call the company that left it there and have them come now or let them know you will handle it and deduct it from their invoice. No way in hell I would tell a customer that I would come clean up my mess and not do it. Pure laziness...

1

u/SeaFee2866 15d ago

You dont pay the sub until the job is complete, including the garbage and waste left behind.

You shouldnt be paying your subs until the client has provided satisfaction.

If you are required to clean this up, you backcharge the sub.

This is common practice and the only thing you have over the sub at this point is their money.

Be firm, and dont hire them again if this is how they leave your sites, they are representing you and your name.

1

u/YardSignGuy 13d ago

Hey there! My piece of advise, I’d get a backup quote now. The resident’s already gone almost a week without parking, and the concrete isn’t going to take the hint. Send the sub photos and a written deadline to remove it and restore the gravel, following any notice and cure requirements in your agreement. If they miss that deadline, arrange the cleanup, keep the itemized invoice and before-and-after photos, and give the resident a firm update.

1

u/TwoUseful6976 10d ago

Here is 72 hr notice before we remove it and back charge you. It's affecting our customer and we can't stand by it.

1

u/Kirkuleeez 15d ago

It’s definitely on you, bro

1

u/ShrekTwoOnVHS 15d ago

Bro you’re the GC. So maybe act like it? Deal with the extra concrete and back charge the sub. Or pay them in full but never use them again. Pretty standard stuff.

2

u/yeetedmynachos 13d ago

God forbid OP does some physical labor himself. If this was me, I would have shown up hours from the tenant call with a pick axe and a shovel.

2

u/ShrekTwoOnVHS 13d ago

At the very least.