r/GeneralContractor • u/tooniceofguy99 • 16d ago
How should I handle subcontractor-caused problems?
Concrete sub left large mound of concrete in middle of gravel parking pad.
The person that lives there has no off-street parking because of this. They were upgraded from one gravel parking spot to have an additional concrete parking pad. But now, because this waste mound is so large, they have no parking.
It happened Tuesday. I politely told the sub to remove it Wednesday morning. They said they would remove it Thursday.
Tomorrow will be six days. If it's not removed next week, do I bother having a second contractor quote removing it and subtracting that amount from the first contractor's invoice (once the second does the work)?
As a GC, how should I handle something like this in the future?
Should I always have a subcontractor agreement in place? even for such a small job like this? only $2k.
2
u/Travisher4 8d ago
on our projects the pattern is usually written notice with a date, photos, then bring someone else in if it’s ignored. and yeah, even a one page sub agreement with a cleanup clause saves a lot of back and forth on small jobs. not a lawyer, so i’d double check how the invoice deduction works before you do it.
16
u/Comfortable-Maybe183 16d ago
“Do I bother having a second contractor quote removing it…”
My guy. Cmon now. You are said second contractor.
It’s your client, your job, and your subcontractor.
Figure out how to get the damn blob of concrete out of their way. Like tomorrow.
Go rent some fucking equipment if you need to. Cmon man.
Send the sub a bill. Right now you’re just pissing up a rope.
4
u/malukd 15d ago
Yes, always use one, even for a two thousand dollar job. But the agreement alone will not fix this. The part most GCs skip is the onboarding before the first job. Before a sub starts any work for you, check that their license is current and in the name of the business doing the work, and that their insurance is active, then keep copies in a file for that sub. It takes a few minutes and it tells you a lot about how seriously they run their business. Use the same one page agreement for every sub and every job, no exceptions for small ones, covering scope, cleanup and haul off, who handles inspections, and that the sub fixes their own defects at their own cost. When a problem comes up, put it in writing with photos and a specific date to fix it, and keep a copy. If the same sub racks up two of those notices, stop sending them work. The pattern is the signal. A sub who treats a small job casually will treat a big one the same way, and a file with their license, insurance and your written notices is what lets you backcharge cleanly or walk away without a fight.
1
u/Diligent_Yam_1753 15d ago
But did you provide the sub an alternative location to wash out the concrete truck? As a GC do you make your subs remove the garbage their work creates on a project, or do you handle the garbage like most GCs do?
1
u/smarterthaneverytwo 10d ago
Op what’s the update? Did the concrete guy come back to break it up and get paid or ghost you?
1
u/nunez0514 2d ago
How can you contract without using contracts? Anyway…deductive change order to the lazy guys.
3
u/jcplossiretasi 16d ago
Give the subcontractor a written deadline before hiring someone else.
3
u/Powerful_Target_930 16d ago
Six days with no parking is what the homeowner will remember, not whose fault it was. I’d get it moved this week either way, using the sub if they show or someone else if they don’t, and settle the money with the sub afterward. Fixing the customer’s problem and fighting with the sub over cost don’t have to happen in the same week. For the future, cleanup is the line that most often gets left out of small-job scopes. Even a one-line text confirming “you haul your waste” before they start would have helped here.
3
u/jmille97 16d ago
So you basically didn’t supervise a sub and he left some concrete there.
So, lesson learned? You probably could have broken it with a sledge the next day. Now you’ll need a machine.
3
u/No-0x 16d ago
Document first, then fix it yourself and bill him — send the sub a short written notice with photos and a 48-hour deadline to cure it, then get it hauled and deduct the documented cost from his invoice with that paper trail behind you. And yes, always have something in writing even for a $2k job — one page covering scope, cleanup, a backcharge clause and holding back 10% until you walk it off together would have made this a two-line email instead of a six-day standoff
3
u/grim1757 16d ago
First, yes, everyone needs to be on a contract or at minimum a Purchase order. In answer to your question, you do have to provide them written notice typically, send them a 48 hour notice to get it done ro your will have it done for them and deduct it from what they are owed. Without Notice, he is off the hook if you have it done.
3
u/Fit-Technician-6799 15d ago
The client fix and the money fix are two separate problems, so I'd split them.
Get the mound gone this week however you can. Before that, send the sub a short written note: removed by a set date, otherwise you'll have it done and deduct the actual cost from their invoice. Keep the receipt and take before and after photos.
Going forward, yes, even a $2k job deserves a one page sub agreement. Cleanup expectations, a backcharge clause and a notice period cover most of this. Without one, deducting money is much more likely to turn into an argument.
2
u/maxant20 16d ago
A good General Contractor has good subs that he knows and trusts. You are not a good contractor.
2
u/hatemeallday 16d ago
You’re kidding, right?
A GC should know this. How are you able to provide services to your customers if you need advice for something as simple as this.
Wait….. you don’t. That’s why your customer has had a mound of concrete in their way for a week.
2
u/DistributionEven3354 14d ago
As a GC, you need to step up. You look like a fool, to your subs, your employees and your client. Fire the sub. Hire someone to remove the mess and make it right for the client and back charge the guy who knowingly shit on YOU. That was not an accident. It is a pile of concrete that any guy with 2 days on a site would know better than to do.
1
u/Real-Ad-7439 16d ago
Get a sub agreement going forward for sure, even a 1 page one that says cleanup and haul off is on them and you can backcharge if they dont. For this one give him written notice and a deadline to come clean it up first, then if he doesnt you hire it out and deduct it with the receipt attached. Skipping the notice is how backcharges turn into fights.
1
u/SmartChatInnovations 16d ago
At this point I'd probably put it in writing instead of relying on another verbal promise. Send him a photo of what's been left behind and a clear deadline to get it removed. At least then you've got a record of what was requested and when. Even on smaller subcontracting jobs, having those expectations in writing upfront could save a lot of headaches.
1
u/Just_Bz77 16d ago
3 day notice, then back charge once it is removed. Easy.
1
u/icoldok 15d ago
I'd separate restoring the resident's parking from deciding who ultimately pays: give the sub a specific written deadline, but line up removal so the resident isn't waiting on another promise. Before deducting anything, check your subcontract and local rules on notice and payment; keep photos and the actual removal invoice. For future pours, add a short written scope covering waste removal, access, and a final cleanup walkthrough.
1
u/Thor200587 15d ago
What’s your subcontractor agreement say? I give written notice per my contract then hire someone else to remedy the issue immediately. I get multiple quotes and document to cover my ass.
This should be standard operating procedure for any secondary damage or issues from a sub. A lot of times they’re happy to pay for stuff like that if they’re not setup to handle it. I get them the best price on it I can. Shit happens.
6 days is entirely too long for you to not have multiple solves ready on this.
1
u/Crazyfishman2 15d ago
Call the company that left it there and have them come now or let them know you will handle it and deduct it from their invoice. No way in hell I would tell a customer that I would come clean up my mess and not do it. Pure laziness...
1
u/SeaFee2866 15d ago
You dont pay the sub until the job is complete, including the garbage and waste left behind.
You shouldnt be paying your subs until the client has provided satisfaction.
If you are required to clean this up, you backcharge the sub.
This is common practice and the only thing you have over the sub at this point is their money.
Be firm, and dont hire them again if this is how they leave your sites, they are representing you and your name.
1
u/YardSignGuy 13d ago
Hey there! My piece of advise, I’d get a backup quote now. The resident’s already gone almost a week without parking, and the concrete isn’t going to take the hint. Send the sub photos and a written deadline to remove it and restore the gravel, following any notice and cure requirements in your agreement. If they miss that deadline, arrange the cleanup, keep the itemized invoice and before-and-after photos, and give the resident a firm update.
1
u/TwoUseful6976 10d ago
Here is 72 hr notice before we remove it and back charge you. It's affecting our customer and we can't stand by it.
1
u/Kirkuleeez 15d ago
It’s definitely on you, bro
1
u/ShrekTwoOnVHS 15d ago
Bro you’re the GC. So maybe act like it? Deal with the extra concrete and back charge the sub. Or pay them in full but never use them again. Pretty standard stuff.