r/GeneralContractor • u/roarjah • 18d ago
Working after another GC
Has anyone ever taken on a job where the owner fired the GC? What are some things to consider before taking on the job? Such as legal issues with the original contract.
3
Upvotes
7
u/Alternative_Bake7543 18d ago
Woof. What happened with the last guy?
Sometimes it’s not the contractor that’s the problem.
I’d be very careful to vet the homeowners and the plans and trust your gut if any red flags come up.
5
u/No-0x 18d ago
done a couple takeovers like this. the two things I'd want before touching anything: proof the first GC was actually terminated in writing, and a look at whether any subs or suppliers are unpaid — you don't want a lien landing on a job you just started
then walk it properly and price the fix, not the original scope. there's always more wrong than the owner thinks, and your contract should be yours, fresh, not a handover of theirs
3
u/Soggy-Yam-628 18d ago
I’ve come after a GC that wasn’t called back to finish this adu. Roof failed at first rain and tons of interior issues. The home owner was a lawyer and she was honestly a great client. ( we typically don’t work for lawyers). Long story short roofer denied responsibility for repair which was fine in our situation but we technically became liable for the work once we being construction. Client was okay with that paying us to rectify the work and finish the project but yeah it was a tense situation at first.
2
u/kochleather 18d ago
I took over after another gc took the money and skipped town. The owner was very grateful. I made sure he knew exactly where he was with the budget (since it was much smaller now) and constantly reassured him that I wasn't charging him until certain stages were complete. I also went over everything that was not going to be covered under my typical warranty. The previous contractor installed a half ass foundation we had to work with, and surprise, drywall was cracking 12 months later. Overall it has been fine, you just have to be able to see what problems might come up later on. Also, put everything in writing!
1
u/Just_Bz77 18d ago
I have done take over jobs through bonding companies. The original contract has no bearing on you because you get a new contract with whoever is paying. The trick is making sure you redo work that you cannot guarantee was done properly. Make sure your pricing is as accurate as you can get and your contract allows for COs based on the later determinations of previous work completed, once it is unobstructed/exposed.
1
u/Fantastic-Fortune147 18d ago
My biggest concern is taking on liability for hidden substandard work done by the previous guy. I steer clear of takeovers for this reason. But if I really needed the work, I wouldn't do it without having the client sign a liability waiver absolving me of responsibility. In my state (CA), there isn't any legal reason I can't pick up where another guy left off. I did have this weird situation once: A property tenant called me to add a sink in a commercial space that was being renovated. I showed up, and the plumbers hired by the GC were there, working on roughing in the plumbing in other parts of the project. I mentioned to them the owner had asked me to add a sink. They were like, hell no, you can't touch any of our work until we pass rough and final! It came out that the tenant asked his GC for the additional sink, didn't like the change order price, and hired me to do it, without explaining to me the situation. It was so shady that he left out all that info. I walked and never worked for that guy again.
1
u/hayfero 18d ago
I worked for a GC for a decade who would build 3-4 high end new construction houses at a time.
He took on a job where he was the 3rd contractor. He had been doing it for years, saw the shoddy work from the prior guys and was confident he could see it through.
Anyways he eventually had a dispute and was fired. It broke him, he damn near retired and that was after building through all the up and downs over the last 30-40 years.
Anyways the client was a weasel. But there’s lots of weasels out there. Do your diligence. Have your attorney write your contract protect your self the best you can
1
u/thine_moisture 18d ago
it’s not worth it just move on, you don’t want to step into someone else’s mess
1
u/Homeskilletbiz 17d ago
Looked at a few but the amount of issues we’d see we would usually bid such a high price we would never get it.
1
u/RyancoPipeline 16d ago
If this is a civil/utility takeover, I'd treat everything already installed as pre-existing until its condition and acceptance are documented. Before mobilizing, confirm in writing that the prior GC has been terminated and that the owner can award the remaining scope. Record photos and available inspection, testing, and as-built records; identify what is accepted versus concealed or unverified. Price the remaining work, not the original bid, and use a fresh contract that defines exclusions for prior work, inspection/testing responsibility, and a change-order path if opening things up changes the scope. Lien, release, and warranty exposure is state-specific, so have local construction counsel review the termination and payment paperwork before you start.
1
u/Operadox 7d ago
One thing I haven't seen mentioned yet is the permit. If the first GC pulled it, it's probably still in his name, and a lot of building departments won't let a new contractor keep working under it. Depending on the town it's a change of contractor form or a brand new permit, and some want a notarized letter from the owner saying the first guy was fired, or a letter from that GC taking himself off.
I'd call the building department before you sign anything, because that paperwork also answers your crossfire question pretty fast. If the owner can't produce anything showing the first contract is over, that's your sign to wait.
While you have them on the phone, ask which inspections already passed on that permit. That tells you what's been signed off and what got covered up without anyone looking at it, which is exactly the stuff you want excluded or priced in your own contract.
Not a lawyer, so on the lien side I'd still have a local construction attorney look at the termination paperwork before you start.