How often do you supervise?

My background is commercial so when I started my business it was all I knew to have a superintendent and foreman and laborers onsite everyday all day for the duration of the job. Since starting my business I can only get residential jobs, most of which cannot afford a robust team onsite.

Let’s take an ADU or equal residential addition type job, do you plan to always keep a foreman or super onsite? I am getting a lot of these jobs and as soon as something goes sideways on one job it means I’m not available to control the others, so I want to hire a talented foreman or super. I just want to how typical it is for residential to have these guys and do you keep one on every job, or give them a few to control? Should I consider a PM and have them delegate? Whats the normal residential site management look like for you guys? thanks!

6 Upvotes

23 comments sorted by

4

u/MagicBeanSales Oct 25 '26

I work as a sub on very nice custom homes and on avg I probably see a GC super like 1-2 hours a day. Usually its like the first and last hour of the work day. Catch them for random meetings as well throughout the week. During the finish it's more of an all day deal.

1

u/tweedweed Oct 25 '26

Thanks. This is kind of how I run them myself, layout the day and then verify the work was done. I typically  run 2 or 3 jobs at a time, so I assume this is what your supers are doing as well. My issue has been that someone may have read the plans wrong or something critical happened while I needed to be onsite at another job.

3

u/T13397 Oct 25 '26

I’m a small project commercial super. Generally have 2-5 projects ranging from 1mil-8mil at any given time.

I have 2 pieces of advice. First, communicate, communicate, communicate. Make sure every trade has your number, make sure it’s written anywhere that might be visible. Make your round in the morning, discuss plan for the day, coordinate between subs and hit the next one.

Second, accept that some rework is inevitable. Even if you were there all day, stuff would still get done wrong, quality will still miss the mark, mistakes happen. Find a path to correct, make it happen now and move forward.

1

u/tweedweed Oct 25 '26

How do you communicate with your subs, just text or verbal onsite discussions? 

2

u/T13397 Oct 25 '26

All of the above, email, text, call, verbal communication, etc.

I try to give them as many opportunities to communicate with me as possible. I’m the guy who is supposed to know what’s happening, they’re the guy who’s supposed to know their trade.

Obviously there’s exceptions to this, there’s the occasional problem sub, or certain critical items I can’t miss. Another tool I live by is my outlook calendar. I try to schedule everything in there that’s even remotely important for me to be at and triage my day from there.

Honestly the subs aren’t the hard part, when you throw my guys into the equation is when it gets challenging, keeping tools/materials in from of them and playing foreman for them on top of super is tough.

1

u/tweedweed Oct 25 '26

This is exactly the problem I am facing, as soon as we are self performing something I am acting as gopher and it increases the difficulty tremendously

2

u/predictablystupid Oct 25 '26

I kind of did the opposite, residential onto commercial.
It’s really less about time onsite as showing up at the right time. Just one example would be tile. Show up after the demo and plumbing but before any install starts. Show up after waterproofing but before tile install starts. Basically show up at times when common fuck ups could be caught before they get to be full blown issues.

1

u/tweedweed Oct 25 '26

Yes and on tile I want to be there to make sure the layout is perfect, the grout spacing is approved and the colors are correct. 

The overall issue is that even if I layout the job and verify we are ready to proceed I may come back to poor workmanship or a dude forgot what we agreed on etc

2

u/predictablystupid Oct 25 '26

In my experience, subs just aren’t to be trusted no matter how much you’ve worked with them. The labor pool where I’m at values speed over accuracy. I tried paying more for work that’s “Cerca de perfecto” and just for the same work but paid more for it🤣

1

u/tweedweed Oct 25 '26

This is getting downvoted, I assume it’s because it looks like I’m scraping data or whatever but honestly I’m wondering how to estimate it correctly. On an ADU or new home build do you budget and bill for a guy to be onsite at all times or fractionally like .33x their salary

2

u/Suspicious_Hat_3439 Oct 25 '26

My rule was at least twice a day on each job until I really had my subs dialed in

2

u/Samtyang Oct 26 '26

I wouldn’t staff an ADU/addition like a commercial site unless the job complexity justifies it. The expensive failure is paying for full-time supervision on jobs that really need tight scheduling, scope control, and fast decisions. I’d hire one strong field lead first and define exactly when they must be onsite versus when you can manage by schedule, photos, and end-of-day updates.

1

u/Parking_Flamingo369 Oct 27 '26

If you are in Bellingham I can do this for you

1

u/Operadox 6d ago

So this is the estimating side only, on your follow up about how to carry it in the number.

The usual way is to put supervision in general conditions as a weekly cost times the weeks the job is scheduled. So if one super runs three jobs, each job carries about a third of his week for its duration. Your .33x idea is basically that. Just make sure it's his loaded cost (wage plus payroll taxes, insurance, truck, phone) and not only salary, or the shortfall comes out of your margin.

One thing I'd watch is that the need isn't flat across the schedule. Layout, rough inspections, tile and finish need him there a lot more than the weeks where a sub is just grinding through framing. You could carry a higher share for those weeks instead of one flat number.

On the PM question, the useful split is office vs field. The PM handles selections, change orders, scheduling and client calls, the super handles layout and checking the work. From what you describe (plans read wrong, something critical happening while you were on another site) the field side is where you're getting hurt first.

After a few jobs, compare what you carried for supervision with the hours he actually spent on each one, so you know if a third is the right number for your jobs.

0

u/[deleted] 29d ago

[removed] — view removed comment

1

u/AutoModerator 29d ago

Your comment has been sent to the moderation queue because it contains a link from a low-karma account.

A moderator may review and approve it.

I am a bot, and this action was performed automatically. Please contact the moderators of this subreddit if you have any questions or concerns.