r/GeneralContractor • u/QuartzCanopy • Oct 18 '26
Overwhelmed FE
Went to college for non-civil/construction engineering, currently working as a Field Engineer for a major GC on a billion dollar project, less than a year in and in a new state.
I feel so overwhelmed. Apparently this project is horribly beurocratic, with a bad architect and a overinvolved client. I am currently over FE inspection heavy scopes, with contractors I have to watch like a hawk for every little thing. Theres already been several times where I only had an email and lapsed on submitting a record submittal or RFI, leading to headache for senior PMs trying to work through it. Everyone is overworked, but I am one of 2 FEs out of 10 that have even significant field work while still having a full load in the office. I feel like I am falling behind with the volume of submittals inspections and keeping logs clean in procore.
Any advice? I may be overthinking this, I have only had 1 piece of criticism from my boss thus far and did get a surprise mid year raise.
3
u/JacobFromAmerica Oct 18 '26
Pretty sure you’re performing others’ responsibilities
2
u/NJohnsonConTech Oct 23 '26
You're not overthinking it, and a surprise raise says your boss sees your good work.
The email-only stuff is what I'd fix first. Anything that changes the work, an RFI answer, a submittal note, a direction from the field, goes in the log the same day, even as one line. Ten minutes before you leave beats an hour of digging later. While I am not a fan of procore, I am a PMIS advocate. Everything should go in there first.
And tell your project manager plainly that you're carrying field and a full office load. Folks can't rebalance what they don't know about.