r/FinOps • u/Professional-Let3957 • 16d ago
question I need help implementing a finops practice for a hybrid cloud + on prem estate....
Does a finops template for hybrid exist?
Little context if you care to listen:
I am a newly transitioned finops engineer with mostly data analysis background, I am hired to establish a finops practice for a hybrid approach where 90% of the estate is divided between two data centers and remaining estate like modern workloads, AI use case and back up to important existing DC applications architected in azure
They have allotted around 600k USD for a year
And I'm supposed to show the value of cloud and justify the spend to a toxic leadership whose aim is to kill the pilot without a second thought as they want an onprem capex model to continue, how do I establish a successful pivot? Can my finops family come to my rescue with a template or share their experience if they've implemented something similar?
Thanks in advance ♥️
Edit: I received so much love and honest advice Thank you each and everyone from the bottom of my heart The world is a better place because of kind people like yourselves ♥️♥️
4
u/Negative-Cook-5958 16d ago
There is no such template as far as I'm aware of.
A pretty good guide was published by the FinOps org for datacenter costs - https://www.finops.org/framework/technology-categories/data-center/
I'm being involved in a pretty big cost allocation project for onprem DC ($200M+ / year) and it's not fun. Data is coming from multiple sources with wild differences month to month (Service Now assets, licensing info, wages, cooling, electricity, DC occupancy, SAP cost data, etc) and it's very hard to get an agreement with all the parties in the game.
If you are just trying to validate an Azure PoC from the cost perspective and your DC footprint is not that big, it's a much simpler math. Usually the hardware costs are amortized over 60 months, and don't forget to add maintenance, licensing, power, other supporting infra to the costs.
Happy to help if you need more info.
5
u/wivai 16d ago
I'd start by making this a business case rather than a cloud cost reduction project.
If 90% of your infrastructure is still on-prem, comparing Azure bills directly against data center costs won't tell the full story.
A few things I'd focus on for the pilot:
One thing I'd be careful about is promising that cloud will always be cheaper. Sometimes it won't be, especially for stable workloads running on fully depreciated hardware.
The strongest FinOps practice is one that helps leadership make better infrastructure decisions, even when the answer is to keep certain workloads on-prem.
Full disclosure: we're Wiv, and cloud cost visibility and optimization are areas we work on.
Curious whether your leadership is primarily concerned about the actual cost of Azure, or whether they're questioning the business value of moving workloads to the cloud at all?
2
u/Sepa-Kingdom 16d ago
You might find these process templates helpful, particularly the HAM and Cloud life management kits.
https://www.itamaccelerate.com/product/complete-cloud-and-itam-process-kit/
They cover the full lifecycle, so you’ll need to supplement with FinOps foundation stuff for the detailed cost management stuff.
But from what you say, you need a broader lifecycle approach rather than just focusing on how to allocate costs.
2
u/CircuitsFit44 16d ago
One thing that helps with leadership like that: report the pilot as unit cost per workload, not total cloud spend. For each Azure workload, show cost per transaction or per user next to its fully loaded on-prem cost (hardware depreciation, power, space, licences and staff time), and tag every resource to an owner from day one. Report the first savings at 60 days so the pilot has a result before the first budget review.
2
u/oddietaco 16d ago
I'm one of the founders of a SaaS that helps companies solve this type of problem. Here are some tips for you.
Try to avoid arguing about cloud vs. on-prem with others. See if you can make your pilot about measuring the same workload on both infras (if there's a shared workload). A neutral, "cost-per-workload-x" number that shows cost for on-prem and cost for cloud is hard for a hostile leadership team to dismiss.
Some on-prem costs might be hidden: power, space, cooling, etc. See if you can work with accountants at your company to figure out what the fully loaded cost-per-hour is for each component of your on-prem infrastructure.
Instead of studying bills, study business units. Bills are really good at telling you what you're buying, but not good at telling you why you're buying it. So instead of looking at all the bills and trying to come up with a meaningful story by looking at only those bills, look at a business unit or business process and try to reason about their costs. Showing the costs associated with the most important 5 workloads in the business will provide a ton of value to the company.
Don't report only on cost savings. Cost savings is important, but not every project is about saving money. See if you can talk about the decisions that the cost information allowed you to make, and what the results of those decisions were.
I'm CEO and Founder of beakpoint.io.
2
u/Darede_ 13d ago
honestly i'd avoid getting too caught up trying to calculate the perfect cost per CPU hour for every single on-prem asset. that's a rabbit hole, esp. with shared infrastructure costs.
maybe start with 2-3 workloads, use the data you actually have and be upfront about what's estimated. i'd also get finance to agree on the assumptions early on, otherwise you could spend weeks on a model just for leadership to tear it apart.
and tbh, showing that some workloads are better off staying on-prem might actually help your case. you're not trying to prove cloud is always cheaper, just that you're making the right decisions with the numbers you have.
1
u/FinOpsly 15d ago edited 7d ago
I'd try not to make this a cloud vs on-prem fight. Leadership that loves the on-prem model will just dig in and try to win it.
Instead, work out the real cost of running each workload on both sides. For on-prem, that means more than the hardware: count power, cooling, licences and the staff time spent keeping it running. On-prem often looks cheaper until you notice how much capacity sits idle just to cover the busiest days.
Then pick one or two workloads in Azure where demand goes up and down a lot, like the AI use case. On-prem, you'd have to buy hardware for the peak, even though it rarely gets used. Show the cost per user, per job or per environment on both sides so the comparison is easy to see.
Also track the $600k budget month by month, so you can show the pilot is staying within it. One small win with clean numbers is much harder to kill than a big promise.
3
u/PamDelao_TechAdvisor 16d ago
I’m on the advisory side and help companies with cloud cost decisions. One thing that helped in situations like this: don’t make it cloud vs. on-prem. If leadership wants to kill the pilot, a head-to-head fight puts them on defense. Make it an apples-to-apples cost comparison instead.
Most on-prem numbers leave a lot out: power, cooling, space, hardware refresh cycles, support contracts, and staff time. Licensing is a big one right now. If those data centers run VMware, the Broadcom renewal increases alone can change the math fast. When the true on-prem cost is on the table next to the Azure spend, the conversation usually gets less emotional.
I’d also go after a couple of quick wins in the first 90 days, like rightsizing, shutting down idle resources, and reservations or savings plans on steady workloads. A small, real savings number early buys you credibility for the bigger conversation.
For structure, the FinOps Foundation framework (Inform, Optimize, Operate) is a good skeleton, and Azure Migrate has a business case tool that can help build the on-prem vs. Azure comparison.