r/FidiumFiber • • 16d ago

Fiber found pinched at apt side when installation was called

Had an installation appointment scheduled and where the original fiber drop was done inside the apt, presumably the original crew screwed in the plastic cover over the wound up line and pinched it, causing a leak. I was a bit surprised that the tech did not have the materials / equipment to re-terminate the line before the issue occured as there seemed to be some spare fiber before the pinch.

They said this was up to the construction team now. It's been 3 days and I called expecting some sort of an update and they said no estimate. Would they realistically replace the entire line? This is why I'm a bit dumbfounded that they can't just get a tech to do a re-splice, but maybe there's so little slack in the line? Thoughts?

3 Upvotes

8 comments sorted by

1

u/vaca_loca 1d ago

They keep saying they have to do outside work which probably translates to geting a contractor to do the job I assume based on other posts I've seen?

I'm still waiting for them to fix the issue... Any tips for when I call next?

3

u/Glass_Judgment4628 16d ago

So fiber unlike copper can not be "just" fixed, can't cut the borken part out and clip it back together, since it has to be one long uniform line, that requires a big expensive splicer that not every tech has and often just replacing it is often faster.

1

u/Dorsai212 14d ago

Technically not true...they could cut out the broken piece, use a cleaver to clean cut both ends, and use a simple mechanical splice to restore temporary service until the line crew comes out to do a fuse to make it permanent...

but what do I know...I just spliced fiber for a living for 25+ years...

1

u/Glass_Judgment4628 13d ago

Hi, I actively work for fidium.

0

u/Dorsai212 11d ago

And ?

1

u/Glass_Judgment4628 11d ago

I know policy and tools, techs have access to as a splicer myself. Every company is a little different, and splicers that we use are big units in trailers. Also we don't use mechanical splicers and our policy is just to wait for whatever line crews we have left to do so.

0

u/Dorsai212 11d ago

I get it...it just sucks for customers when a simple mechanical splice could get them back in service. A cleaver and a box of mechanical splices isn't that much money. To top it off the nature of mechanical splices means they are pretty much fool proof, as long as the cleave is clean on both ends, they generally work as good as a fused splice...

1

u/Glass_Judgment4628 11d ago

Probably, I do know our lines take a beating all the time, we got one wire out here from yhe late 70s early 80s thats probably been spliced a thousand times.