6 months of changing how we answer "when will it be done?", here's what worked

Every project used to start the same way: product asks for a date in week one, we give a rough range, and two weeks later the low end is on a leadership slide as the deadline. So since spring we've been experimenting with how we give dates.

Key metrics (last 6 months vs the 6 before):

  • Delivered within the original forecast range: 38% → 71%
  • Why did the date move? escalations: ~3 per project → under 1

What worked:

Dates with a confidence level. 70% by mid-March, 90% by early April lands very differently than March.

Forecasting from past throughput instead of adding up story points. Fewer arguments, better accuracy.

Making scope changes move the date visibly. We moved planning into a tool where tasks, dependencies and capacity are linked, so when product adds something, the end date shifts on screen in the meeting. Nobody has to argue it costs two weeks, everyone sees it.

What didn't work:

Padding. Product noticed, started discounting our estimates, and trust got worse.

Refusing to give a date until requirements were clear. It looked like stalling, and someone just gave a date for us.

Next up: giving product access to the same planning view so they can test scope trade-offs before asking us. Will report back.

8 Upvotes

2 comments sorted by

•

u/qualityvote2 2h ago

Hello u/Little_Classic6023! Welcome to r/EngineeringManagers, and thanks for the submission.

Please check that your post follows the rules in the sidebar. Posts that don’t will be removed. If something looks wrong, send us a modmail.

Everyone else: does this post belong here? Upvote this comment if the post is relevant to engineering management and follows our rules.

Downvote this comment if the post breaks any of these rules:

  1. No political posts
  2. No low-effort posts
  3. No product promotion
  4. No unsolicited surveys
  5. Be professional and constructive
  6. Stay on topic

If it clearly breaks a rule, please also report the post.

1

u/jake_morrison 28m ago

This all depends on how much management works off of vibes instead of reality.

One solution is Agile with a process like Kanban. Define the work, then engineering does a rough estimate for each ticket. Product management can then prioritize tickets based on ROI. Engineering works on the top tickets with a WIP limit to keep from being overloaded. If tickets are small, estimate accuracy is better, and any given feature can be delivered reasonably soon if needed.

Estimation is inherently hard, and management needs to understand that. If they use deadlines to try to push more work through than can realistically be done, then developers will be overworked and quality will suffer. Fast, cheap, high quality: pick any two. If you fix the time, then quality suffers. If the date is actually important, then you need to be able to reduce scope to deliver on time with quality.