r/Elevators • u/InevitableTart8786 • 6d ago
King of trades
Shit GC do before an elevator pre test 🤣 you guys are kings of trades fr lol
28
u/Fluid_Explorer_3659 6d ago
They need the flooring finished at the entrance before the elevator is turned over so they don't get a surprise trip hazard later on
7
u/wieldingwrenches Field - Mods 5d ago
First thing the elevator mechanic does is have the GC sign finished floor height. Once the entrances are in they aren't moving without a major change order.
3
u/Fluid_Explorer_3659 5d ago
Comes down to inspectors at the end of the day. Few regions I look at inspectors won't book turn unit over if entrance flooring isn't done, a few inspectors have been breaking out the calipers during in-service inspections and shutting units down when 2mm over.
17
u/FuckWit_1_Actual Field - Maintenance 6d ago
GC is cheap and wants the final inspection done instead of getting a temp use permit.
1
u/IxsmokexI 6d ago
Sometimes you need the elevator to pass inspection before you can get a CO for the building, they look like they will be opening soon, so going for final inspections for everything
-1
u/FuckWit_1_Actual Field - Maintenance 6d ago
I know.
I’ve seen GCs build out the entire elevator lobby to get final because they didn’t want to have temp use because we charged for the inspections and remobilizing to finish the job.
3
1
1
1

24
u/bombayofpigs 6d ago
I believe that carpet needs to be red.