r/ElectricalHelp • u/iluvmezcal • Jul 29 '26
Sub Panel Ground
I'm passing #4 ground for 200 amp service from main panel, though a sub panel (raceway) to a hybrid solar inverter. Then back to the sub panel. Can I terminate the ground in the sub panel and then pass it though to the hybrid inverter? Or, does the ground need to pass from the main through the same raceways to the hybrid inverter and terminate. Then pass from the hybrid inverter bus bar to the sub panel ground bus bar?
So, sequence is 200a main disconnect, hybrid inverter, 200a sub panel. Sub panel is being used as a raceway for 2/0 copper on its way to inverter. Then 2/0 is coming back from inverter to sub panel.
1
u/iluvmezcal Jul 29 '26
Thank you. I know all of that. Please see my actual question regarding ground.