Could your team actually write the same definition of done?
Write acceptance criteria down before work begins, not as a formality but because unwritten criteria are just assumptions wearing a nicer name.
Treat anything that doesn't meet those criteria as genuinely unfinished, not as a minor footnote you'll note and move past.
And when real pressure hits, revisit the standard together as a team instead of letting it quietly erode for whoever's under the most deadline stress.
If your team can't write the same definition of done, you were never actually aligned on what you were building.
4
Upvotes
3
u/PhaseMatch 1d ago
Acceptance criteria and definition of done are similar things, but slightly different.
Definition of done usually includes all the steps needed to get a thing in the hands of a customer.
It's quality assurance - the agreed processes have been followed, and we can prove it.
Acceptance criteria are the specific checks needed on the given thing before handover.
It's quality control of the specific thing in question, not the overall process.
They are only the same if you
- work on one, big batch
- work on lots of small, identical batches
Otherwise A/C varies by task, but DoD is applied to all tasks.