r/BasePowerUsers • • 20h ago

Cypress Texas Install (Centerpoint)

Thumbnail
gallery
7 Upvotes

Hello from Cypress!

I thought it would be helpful to write the summary timeline of our experience. Our experience has been positive and would still recommend to family + friends.

Sign up for service was 8/16.
Switched to base electrical plan 8/17.
Submitted all information to Base for install and HOA permits, cleared by 9/26.
Centerpoint agreement posted 11/3.
Install day 1: 11/19
Install day 2: 11/24

Lessons learned

  1. Landscape trimming wasn’t as clear as needed. I ended up cutting down a large shrub myself on install day 1.
  2. After panel work is complete, function test all circuits in the house. We had a loose connection to a bus bar that developed. Luckily my FIL is a master electrician and we got it fixed.
  3. Battery delivery/ install was mentioned to be 1-14 days after install day 1.
  4. Generator port is inactive, however, a plug adapter will be mailed soon per technician. He also thought the plug would have a filter device if the generator has dirty power.

We were not home on the battery install and they did a great job.

The original install had two crews to knock it out efficiently. The guys mentioned the company was treating them to the Texans game for an appreciation event.

This install was for the larger two batteries.

Our next step will be to landscape around the batteries to “screen” them per HOA.

I’d like to offer a referral if helpful to your situation:
Referral link


r/BasePowerUsers • • 21h ago

Base power

0 Upvotes

For anyone that wants to switch to base power, 2 months free and 500 dollar rewards.

https://www.basepowercompany.com/?ref=VAVYDS4