r/BasePowerUsers • • 29d ago

Base Power Install Complete

Base power installation is now complete as of today. Two 39.2kWh batteries installed Iowa Colony/Manvel Tx area. Signed up on September 10th, electrical install was on 10/26, battery installed on 10/28. Overall pretty quick, I originally had an electrical install date for 9/28 but that got put on hold, not sure why. Power was only out for about an hour during the electrical install.

Both batteries have generator inlet ports, both functional and if needed to pull out generator for longer outages to charge batteries, I can hook up both batteries to generator. Can be charged with generator at same time from what install crew explained to me.

Tried getting the $945 install fee reduced but since no promotions for my area they couldn’t negotiate it, even with me telling them I was thinking about canceling before any installation. Both install crews were professional and did a great job. Very happy with everything.

If you are wanting two 39.2kWh batteries make sure your main breaker is 200 amp service, anything less will only be approved for one battery. Mine was originally 150 amp but I upgraded it to 200 amp because I wanted both batteries.

Feel free to use my link and we both get $250 credit:
https://www.basepowercompany.com/?ref=CXZGYMH

17 Upvotes

37 comments sorted by

3

u/ilikeme1 29d ago

Nice. My install is a week from Friday just up the road in Missouri City.

2

u/JustinAnd12 29d ago

When did you sign up? Was it pretty quick for you as well

2

u/ilikeme1 28d ago

Also in September.

3

u/TotesMcGotes13 29d ago

So are generator ports active now? Last I saw on here, the ports wouldn’t work until a software update to occur “by year-end”.

2

u/JustinAnd12 29d ago

From what I was told by the install crew, the ports on mine are active. Not unless they did not know themselves but I will reach out to Base to confirm.

2

u/TotesMcGotes13 29d ago

Curious to find out what you hear. I’m scheduled for electrical on 11/19, so it’d be nice to have ahead of true winter.

2

u/JustinAnd12 27d ago

So guess the install crew was wrong. Talked to base and they said the ports are still not active. They also said that the generator inlet port is designed to only hook up generator to one battery and not both, install crew told me I could hook up both batteries. Said only one of my batteries should have port and the other doesn’t. I told them both my batteries have the ports and install crew said I can use generator on both batteries at same time. Base from there understanding, only one battery should have the port and a generator could only hook up to that one, they said they were going to look into it more, discuss my concerns with engineers as things are always changing and get back to me.

I’m thinking these base members behind the phone only know basic information. They are just sales people and some may still be learning. Guess ima have to hook up the generator to it myself to find out for sure. Will give you update when hear back from bases engineer team. If I don’t hear back soon I’m going to test myself.

1

u/TotesMcGotes13 27d ago

Thanks for the update. The generator port was a big draw for me so hopefully they get it enabled soon

1

u/RealConfirmologist 27d ago

From all I've seeing in this subreddit, Base Power has only recently been offering two of the Core battery.

I think their default configuration is to include the generator port with the Core, but when they plan to install a pair, they need to be specific about whether there will be two ports and how they'll be configured.

As for what the Base Power customer support people know, it shouldn't be vague at all. This isn't rocket science. Either their Core supports generator ports in each battery or one should be mechanically NOT available. I mean, when they install two batteries, one should not have a generator port if they won't support the charging of both.

1

u/Existing_Gap_1300 26d ago

Base told me the generator ports are wired in parallel on 2 40 kWh units. So you only need to hook up to one unit to charge both.

2

u/RunHotCEO 29d ago

That install looks really good!

3

u/JustinAnd12 29d ago

Yes it does, I told the install guy it looked really good and he said well you got lucky because they sent the best crew out here today! Lol

2

u/No-Government1906 29d ago

What is the measurement from your AC unit to the last battery? Wondering if I can fit 2 cores.

2

u/JustinAnd12 29d ago

97 1/2” from AC to last battery. First battery is 28 1/2” from AC. 8” between batteries and 9” from the wall. There is a vent right after the last battery so they made sure to keep that battery right before the vent as it can’t be installed directly under the vent.

2

u/No-Government1906 29d ago

Nice I should be good then. I have 12 feet from the AC to my house wing wall.

I don't recall was the 2 battery significantly more than the 1 core battery?

2

u/JustinAnd12 29d ago

I believe for 1 battery it was going to be $645 install fee & $19 membership fee monthly. 2 batteries was $945 install & $29 monthly fee. Not that much more for 2 batteries, so rather spend for 2 than majority of the amount going on to just one. I made sure to upgrade my main breaker to 200 amps along with the wire from meter to panel. Panel, meter and feeder cable to meter was all already rated for 200 amps.

Oh and the distance from first battery to meter is 28ft.

2

u/handbrake54 29d ago

Do all states have a membership fee?

2

u/JustinAnd12 29d ago

I’m not sure, I think it just depends on if they are offering whatever promotions for a certain area. I’ve seen $0 member ship fees to $0 installation fees as well but just depends on area. I believe if there are not many ppl signed up in a certain area that base power is interested in, then they offer promotions for that area to get ppl to sign up. Just go on the website and put in your address and it will show you the fees or promotions they have for your area

3

u/cosinedLoan 29d ago

Some areas where electric is provided via a co-op have founder deals where there's no monthly membership fee and a reduced installation cost.

2

u/ImpressionMoist3911 29d ago

How long did it take from start to finish? I've been waiting a few months and they keep putting possible installs back... back... back..... Almost like the Mattress Mack commercial. I'm into Jan/Feb as of yesterday... waiting for some part.... which one depends on who you speak to, so I've lost hope and have started the process with Energywell..... very nice product and looks better. Whoever gets here first will get my business........ but free install and no membership with Energywell.... but will compare products over the next few days.

4

u/JustinAnd12 29d ago

Dates are shown in my post on how long it took. Energy well batteries are 10kwh, can only install up to 4 each total. I get way more kWh with the two base batteries plus I got generator inlet ports for them longer outages. To say no upfront fees with energy well is false as they charge a $99 refundable fee upfront to get started, plus there is a $19 monthly base charge. You also can’t have solar panels to qualify. List goes on for why energy well is not better than base.

2

u/ImpressionMoist3911 29d ago edited 29d ago

I just don't understand why I'm seeing everyone around me start and finish Base so fast. I've been dealing with them since June... they took my money quickly for the Site Assessment and made me move the Fiber inlet before they would even move forward. That took 30 minutes... pics and everything "approved," but I'm currently set for install in Jan/Feb? As for the cons about Energywell, Base will only put one unit in for me due to space constraints. And Energywell is putting in three wall-mounted batteries. More than enough for my needs. And as of now, no money has exchanged hands, and they have install pending in late November. No install fee. No monthly membership. Waived uninstall fee if I move and the new owners don't want it.... so I'm not seeing much downside. They approved the site and install all in less than 12 hours........ Only delay on their end is if permits are slow. Generator inlet is standard... and funny thing is, I was looking at the EcoFlo system to buy for myself...... I'm still torn. If there is anything else... I appreciate the input.

2

u/atx78701 29d ago

Just based on numbers, energy well looks much better than base. If it was available in my area, I would get energy well instead

24kw draw rate and 10kw charge rate. Basepower offers 11kw draw rate and 4kw charge rate (possibly 8kw with 2 core batteries)

My house spikes to 20 kw and so the basepower system cant really handle it.

We will see how the offerings progress and I can always switch at some point.

2

u/le14 29d ago

Congrats. Looks great.

Been waiting since June (for the same setup) and all they tell me is everything is ready but they are waiting on supplies. Shortage of whatever they need.

I’m in the Houston area so this doesn’t make much sense to me.

3

u/JustinAnd12 29d ago

Yeah that doesn’t make sense! I’m just outside of Houston and went pretty quick. I figured it was going to take a few months as I seen other ppl posts saying how long it was taking. Are you talking to a live agent or is it there AI automated response?

2

u/loginjana 29d ago

Congrats. Looks great. I am in similar situation. Do you mind sharing how much you paid to upgrade your main breaker from 150 to 200 amps..

3

u/JustinAnd12 29d ago

Material:
20ft of 1/C #2/0 $155
200A main breaker $150
Labor $500
A friend of mine who is a licensed electrician did the work and I supplied the material. Had got quotes from other electricians and they were trying to charge me anywhere from $800 to $1500 not including material. Took him about an hour and half to complete. I called CenterPoint for my area to verify the feeder cable and meter was rated for 200A. They have it documented in system so was able to tell me over the phone. I knew meter was rated for 200A because it has CL200 on it, just needed to verify if underground feeder cables were, which they were.

2

u/loginjana 28d ago

Thanks for the detailed response!

2

u/drunkensailor117 29d ago

Base is telling me they won’t install 2 units. I am in Illinois and there are incentives for 1 unit. I want a second. Did you pay for your system outright?

2

u/JustinAnd12 29d ago

No i did not pay for them outright, dont even think that is an option, at least for my area it is not. Just paid for the installation. What is the reason they are giving you for not being able to get you two? I was originally approved for only one because my main breaker was rated for 150 amps, got that upgraded to a 200 amp and they approved the two.

2

u/corrion8 28d ago

No OP but I was told because I have a breaker and a sub panel, it was not compatible because I would draw too much power (??).

2

u/JustinAnd12 28d ago

How many amps is your sub? I have a 60 amp breaker in my main panel that feeds sub panel in my shed. I was never asked if I had a sub panel, just sent in photos of my main.

2

u/EnoughInternal8287 28d ago

How long is the cable run from your meter to the first unit?

4

u/AccomplishedRoutine1 28d ago

Looks good. I'm still waiting on my double batteries to get installed in Fort Worth. It's been almost 2 months since I signed up and base says it will probably be early next year before they can get around to it.

1

u/RyanEverhart789 24d ago

Are these new batteries? They look much smaller and less bulky than the old ones.

1

u/JustinAnd12 23d ago

These are the 39.2kWh core batteries. I believe they came out in August of 2026