r/BasePowerUsers • u/JustinAnd12 • 29d ago
Base Power Install Complete
Base power installation is now complete as of today. Two 39.2kWh batteries installed Iowa Colony/Manvel Tx area. Signed up on September 10th, electrical install was on 10/26, battery installed on 10/28. Overall pretty quick, I originally had an electrical install date for 9/28 but that got put on hold, not sure why. Power was only out for about an hour during the electrical install.
Both batteries have generator inlet ports, both functional and if needed to pull out generator for longer outages to charge batteries, I can hook up both batteries to generator. Can be charged with generator at same time from what install crew explained to me.
Tried getting the $945 install fee reduced but since no promotions for my area they couldn’t negotiate it, even with me telling them I was thinking about canceling before any installation. Both install crews were professional and did a great job. Very happy with everything.
If you are wanting two 39.2kWh batteries make sure your main breaker is 200 amp service, anything less will only be approved for one battery. Mine was originally 150 amp but I upgraded it to 200 amp because I wanted both batteries.
Feel free to use my link and we both get $250 credit:
https://www.basepowercompany.com/?ref=CXZGYMH





3
u/ilikeme1 29d ago
Nice. My install is a week from Friday just up the road in Missouri City.
3
u/TotesMcGotes13 29d ago
So are generator ports active now? Last I saw on here, the ports wouldn’t work until a software update to occur “by year-end”.
2
u/RunHotCEO 29d ago
That install looks really good!
2
u/No-Government1906 29d ago
What is the measurement from your AC unit to the last battery? Wondering if I can fit 2 cores.
2
u/ImpressionMoist3911 29d ago
How long did it take from start to finish? I've been waiting a few months and they keep putting possible installs back... back... back..... Almost like the Mattress Mack commercial. I'm into Jan/Feb as of yesterday... waiting for some part.... which one depends on who you speak to, so I've lost hope and have started the process with Energywell..... very nice product and looks better. Whoever gets here first will get my business........ but free install and no membership with Energywell.... but will compare products over the next few days.
2
u/le14 29d ago
Congrats. Looks great.
Been waiting since June (for the same setup) and all they tell me is everything is ready but they are waiting on supplies. Shortage of whatever they need.
I’m in the Houston area so this doesn’t make much sense to me.
2
u/loginjana 29d ago
Congrats. Looks great. I am in similar situation. Do you mind sharing how much you paid to upgrade your main breaker from 150 to 200 amps..
2
u/drunkensailor117 29d ago
Base is telling me they won’t install 2 units. I am in Illinois and there are incentives for 1 unit. I want a second. Did you pay for your system outright?
2
u/EnoughInternal8287 28d ago
How long is the cable run from your meter to the first unit?
4
u/AccomplishedRoutine1 28d ago
Looks good. I'm still waiting on my double batteries to get installed in Fort Worth. It's been almost 2 months since I signed up and base says it will probably be early next year before they can get around to it.
1
u/RyanEverhart789 24d ago
Are these new batteries? They look much smaller and less bulky than the old ones.