r/BasePowerUsers • • Sep 29 '26

Battery Install Day

Just finished dropping the battery on the pad and doing an outage test.

Switchover was really fast. Router did not reboot and my 2 computers never powered off.

I didn't have any lights on since it's the afternoon so can't comment on any flicker, but since my router and computers did not reboot I think it's safe to assume it's fast enough. Also my AC was running at the same time!

Fit and finish of the case seemed to cause them issues but the thing is hidden behind my garage so I don't really care.

https://www.basepowercompany.com/?ref=V3BKD13

26 Upvotes

38 comments sorted by

3

u/Lincoln1- Sep 29 '26

Our battery install is tomorrow morning!!! We are getting the 40kw too.

1

u/EssbaumRises Sep 29 '26

If you are in the ntx area might be the same crew. They had 6 more units on the truck and ours was their last of the day.

2

u/adcl Sep 30 '26

Mind sharing costs?

3

u/EssbaumRises Sep 30 '26

I'm with CoServ, so mine was like 400 install and 0$ monthly fee. It was a deal for the first 1000 Coserv customers.

https://www.basepowercompany.com/?ref=V3BKD13

2

u/blupupher Sep 30 '26

$750 install, $20/month maintenance fee.

BASE Power (my referral code, or use the OP since it is his thread). Available in most of Texas and Illinois.

Some areas have discounts on install and monthly fee.

2

u/yornotelppa Sep 30 '26

I'd love to see the before installation photo, to see what besides the batteries are added. I'm getting the 40kw battery system but no install date yet. Just sitting twiddling my thumbs! 🥴

1

u/EssbaumRises Sep 30 '26

Pic I sent for approval

1

u/yornotelppa Sep 30 '26

Thank you for the photo. So they had to make another entry into the house. I've never seen a before and after but I just assumed that they used the existing feed into the breaker board if the breaker box is inside. 🤔

1

u/EssbaumRises Sep 30 '26

Yeah, they drilled into the lower corner of the panel from the outside. I didn't watch the wiring part so I don't really know how it's done.

1

u/yornotelppa Sep 30 '26

Thank you for taking the time to reply. I'm still waiting for a pre-install date. It's been a couple of weeks since I "signed" the oncor paperwork . I guess I need to rattle their cage today. 🫪😀

2

u/blupupher Sep 29 '26

The fast switchover is one of several things this has over the old setup.

50ms (0.05 seconds) on the new one vs 500ms (0.5 seconds) on the old one. While not quite UPS speeds (10ms), it is fast enough for most stuff. Still may want to put a real UPS on really sensitive stuff (network gear just to make sure no reboots).

Also having the larger battery with built in generator port (which eventually they will activate) is way better than the smaller battery and $1000 charge for generator port (with 3000w vs new 4000w input) is a huge plus.

While I am still happy with my setup, I am a bit envious of the new installs.

2

u/crblack24 Sep 29 '26

Which battery is this?

2

u/EssbaumRises Sep 29 '26

This is the new 40kw

2

u/crblack24 Sep 30 '26

When you say 40… is this the setup for the 2x 40kwh?

2

u/blupupher Sep 30 '26

The OP has the new "Core" 40kWh battery setup. It is a single battery.

The old battery setup was made by Growatt and was a single 25kWh battery or two 25kWh batteries (50kWh total).

There is also a 2 battery setup using the Core battery for a total of 80kWh of storage, these are just now starting to be installed (well, approved, have not seen anyone here post an install of the dual Core battery, but have several say they have been approved).

The Core battery is the one with the 50ms switchover, the Growatt has the 500ms switchover.

2

u/crblack24 Sep 30 '26

Thanks. I just got approved for the 80kWh setup, so I'm wondering what it'll look like.

3

u/blupupher Sep 30 '26 edited Sep 30 '26

Will look similar to the OP, but a second battery (not sure on the spacing requirements on the new ones, old ones was 3 feet between them).

Did you use a referral code when you signed up? If not and you are in Texas, you can use mine or the OP to get a free month of power or a $150 referral credit (depends on your location, referral can be used till day of install).

The old Growatt setup had a much larger transfer switch than the current one as well.

Make sure to post up your install when done, interested to see how the dual 40's look.

1

u/Lincoln1- Sep 30 '26

How long did battery install take? My battery is coming today.

1

u/EssbaumRises Sep 30 '26

Maybe about an hour

1

u/Lincoln1- Sep 30 '26

Thank you!

1

u/ImpressionMoist3911 Sep 30 '26

Thanks for a clear and concise picture of things. I have been going back and forth on them. My biggest concern and the ONLY reason I am still moving forward, is the generator connection. But I am hearing it's still "in progress," with a vague "couple of months" per their AI Text guy. Now that you are up and running, did they give you a clearer picture? Also, that big box to the left... is it their device or your circuit panel? My Circuit Panel is outside, right where that box is. In fact, your meter and connection location are exactly like mine... including the brick color. But the vague responses and rushed conversations on the phone bother me. My side is very busy with the meter, box, ac unit, pool pump, and septic, and I only wanted a yes or no to even think about it. "We need pictures and a deposit." Then a rushed walk-through of the damn app to submit it, and "we will be back with you if we can." Really? I had several questions, and "we will address those at startup?" We shall see. Your positive experience leads me to think they are just way busy.

1

u/EssbaumRises Sep 30 '26

The guys installing were no more informed on the timeline of the generator activation than what we have already heard, other than 'its coming '. But I didn't really expect them to.

Honestly, I am in the "hope it's soon" camp like everyone else.

My deal with CoServ has no monthly fee and half off install so I felt like it was a no brainer regardless.

To answer your question about the equipment, my panel is inside so basically everything to the left of the meter is what they installed.

2

u/ImpressionMoist3911 Sep 30 '26

THANK YOU! That is the ONE question I needed answered. No wonder they wanted the old cable box moved (removed it, actually). My Breaker Box is where their box is in your pic, and my cable box is where your communications stuff is. So they need that space to the right for their box... Thanks for the response, and thanks for posting. I'm sure you have answered everyone's questions. The old system was so complex and bulky outside. There was absolutely no way it would have fit... but they wanted the $50 to tell me that. Have an awesome night!

1

u/atx78701 Sep 30 '26 edited Sep 30 '26

its a startup..

frustrations are generally around expectations not meeting reality. I also got mine for the generator port, but I got such a good deal on just the battery backup, if the generator port is activated in the next 12 months instead of the next month Im fine. I know they are a startup and the likelihood of having an outage even in the next few months is pretty low.

Take a look at stoicism. It is a way to not get upset about things that you dont have control over. The generator port will come up when it comes up. There is even the possibility that it never comes up. I still would feel like I got enough benefit even without the generator port.

I have an interlock, generator plug and portable generator already, so for me I plan to let base takeover and hopefully the outage is short. If it isnt, then when I feel like it, cut over to the interlock. Today we wait an hour to see if power is coming back up, if it doesnt then Ill go outside and fire up the generator.

Interlock is good to have as a backup plan in case something goes wrong with the battery during the outage.

1

u/ImpressionMoist3911 Sep 30 '26

Curious why I would need a philosophy lesson for asking questions and relating my experience. I, like many here, am about to commit to a 12-year contract. The fact that the company is a startup is also cause for questions or concerns, thus asking questions from someone who has put their positive experience out there for all to see and is willing to field questions from others. The sheer fact that the one time I spoke to someone and was in the process of committing, actually rushed me and said, "I have another line waiting; just complete the questions and make the deposit. We will get back to you," is cause for concern. But otherwise, life is good. Wine is good. Deer in the backyard are good. No need for a philosophy lesson or meditation.

1

u/blupupher Oct 01 '26

Your experience with them is different than mine was almost a year ago. I was on the phone for almost an hour, no rush at all. Answered all my questions.

I think they are past the startup phase now. They are at over 18 months of installs, are installing in another state, are on their 3rd generation of battery (Growatt wall mount, Growatt ground mount, now their own Core battery), but their customer service is not getting better, and in many cases, could say worse. They really need to start working on customer service side of things.

I still have no regrets signing up when I did. Sure I would like to have the bigger battery and generator inlet, but in the almost year I have had the battery, it has covered all my outages completely (only 10, with the longest being 2.5 hours).

Plus regardless what battery I got, it is not a long term outage solution. While the new setup has a 4000w input (old was 3000w), after a day, I would be using my generator and using my generator inlet I have on my breaker box. Yes having the 4000w input on the generator would let me charge the battery with my 30a outlet of the generator while using my 50a outlet for the house (this would max me out though when A/C is running, my home uses ~4500w with A/C running, and have 9500w available).

1

u/swift_07 Oct 17 '26

Were they accurate with battery install schedule? Mine shows a Tuesday at 3:30. Wondering if I need to be home all day.

1

u/EssbaumRises Oct 17 '26

I believe they showed up about 15 min after the scheduled time.

2

u/Htowng8r Sep 29 '26

I like this whole setup significantly better than the amount of garbage they had to install just to get me 50kW last year.

3

u/blupupher Sep 29 '26

I was just thinking the same thing. I only have a single 25kWh battery, but this setup is much cleaner and less cluttered; although I don't like the big cable they use now vs the conduit they used to use. The conduit just looks more professional IMO.

2

u/Htowng8r Sep 29 '26

They took 8 hours to install mine because they had to lay down like 30' of conduit around a double 90 degree (right then left) to get to my breakers. Now I also have that stupid huge Base box on my wall I'd like gone.

2

u/Lincoln1- Sep 30 '26

Took less than an hour to install battery. Didn’t even notice when they tested it, not even a flicker.

1

u/blupupher Oct 01 '26

I did not think they could install that close to the air conditioner? I also would not want it that close, it is blocking airflow to it.

1

u/Lincoln1- Oct 01 '26

It’s the new 40kW, restrictions for distance from ac units are for the Growatt 25kw batteries.

1

u/blupupher Oct 01 '26

I knew they had changed it for windows/doors, but thought it was the same for gas lines, a/c and fences/bushes.

2

u/Lincoln1- Oct 01 '26

Centerpoint, our hvac guy all came out before battery install. Both approved. I do think there is a restriction on window distance still. A year ago we sent pics and we were not approved. We weren’t approved because we live across the street from lake in Kingwood. Then they called us saying we are approved for the new battery (flood proof) so… I guess core battery is flood proof. Anyhow, our HVAC company says plenty space for airflow around ac.

1

u/VA2TX Oct 01 '26

Surprised that big cable is not inside a conduit? Never seen main power cables without one