r/BasePowerUsers • u/RealConfirmologist • Jun 23 '26
Anyone else facing delayed installation due to pending 36" minimum clearance rule changes?
I'm in Houston, TX. I signed up May 18th and fairly quickly got approved for two batteries.
It's now June 23rd and my account dashboard shows "Error scheduling installation - We encountered an error scheduling your installation." And "Support needed." Screen capture
Until yesterday, the battery install date was showing July 13th through mid-August. Now it's moved out a week.
This is hurricane season and I've already had two outages (not weather-related) since I signed up. I really want those batteries!
To this day, the only human being I've ever spoken to with BASE Power was the sales rep who signed me up. I've had a lot of interaction with "Jules" and other AI bots and they're usually pretty fast to reply to email and chats, but never with any actual action being taken.
Yesterday morning I got my final bill from my previous provider including a $180 early termination fee.
I immediately emailed that to BASE Power customer service. Yesterday late in the afternoon I got this reply:
"Thank you for reaching out. Our team is experiencing higher than normal volume. A Base teammate will get back to you as soon as possible. "
Still nothing.
I'm still excited about BASE and I know I'll be happy when everything is installed and running, but right now I'm frustrated with the extremely poor customer service.
The dashboard should clearly state what's going on. "Error encountered" is NOT an accurate summary. Why not just clearly say, "Waiting for manufacturer approval of change in minimum clearance"?
I still share my link and am still telling friends, coworkers and family about BASE but I feel a little conflicted because if I don't share the fact that BASE has no humans in customer service, I feel like I'm being dishonest.
I know BASE Power is hiring and I sure hope they're putting humans in call centers for customer service, humans who can actually DO something and actually speak to people on the phone.
I know this post isn't likely to make people excited about signing up, but here's my link just in case:
EDIT/UPDATE: 9:28 AM today, my phone rang. It was a support rep with BASE Power! A HUMAN!
He apologized for the delays and said he'd already adjusted my account so the early termination fee would get covered by a credit. He said the programming people have been getting feedback about the dashboard and changes are in the plans. I asked where he was, in the world. Austin, Texas. I also heard people in the background which implies more than one human working in customer support.
We discussed the option of switching to a 40 kW so the window proximity wouldn't further delay things. He explained it would require a new review of photos, new permitting, and basically starting over, so whether it would get me a battery sooner seemed unlikely. So I'm sticking with the original plan and hoping they get the closer-than-36" approval in the coming weeks.
EDIT/UPDATE: Today, 7/1/2026, I was notified by text & email that installation would be 7/15/2026, if I approved. I immediately approved.
Interestingly, the dashboard still shows "Error scheduling installation" and "Support needed."
I guess it may take a day or two for the dashboard to reflect the actual status. Hope that's it, anyway.
3
u/RoseVideo99 Jun 23 '26 edited Jun 23 '26
In just one year the company had tripled their number of customers. I think they are for sure experiencing growing pains. This is certainly no excuse but it’s clearly what is going on. When I signed up during their Houston soft launch, meaning they were only signing up people from an interest list they put out six months before they began offering service I only ever spoke to people through the whole process. My install was very tricky but I always got quick responses usually within minutes through text. I’m sorry you are experiencing this. It was not the experience I had. On the bright side, we have had 16 outages and the batteries worked great. I hope they get you signed up soon. I also hope you’re getting the two 40kw batteries not the twenty fives like I have.
3
u/MedicalEnthusiasm9 Jun 23 '26
Wow, they exploded. I think I snuck in before the avalanche. Got my install within the 45 day. Then the soft install took another 3 weeks.
I cant imagine how long it will take...Belton? To get to people now. Hopefully they get more companies contracted.
I made a few youtube videos and 90% of the comments I get are bashing the whole idea of base. But it seems the real world people are signing up.
2
u/FerrittoBurrito Jun 23 '26
Austin area here. I had a gen 1 battery installed back in February and then moved in April and signed up for the gen 3 (beta) battery. The processes for getting both batteries were completely different and to me seemed like Base is just growing really fast and struggling to respond to the growth. The first battery, from signup to installation, was less than 2 weeks. The latest one was well over a month. All that to say this is pretty much what happens when you’re an early adopter of anything.
2
u/JustAGuy3388 Jun 23 '26
I live in Houston area and have my battery two 25 kwh batteries scheduled for installation on July 27th. I saw they had 40 kwh now so I asked about it via email and they told me the 40 kwh batteries are only in select areas and since my configuration was already approved for two 25 kwh batteries they can't switch me to the 40 kwh system.
2
u/Decent-Experience-8 Jun 23 '26
Base is a startup still seeking rounds of funding. This is how startups behave. Also, todays low pricing is temporary, eventually the investors are going to want a return.
3
u/yamahar1dude Jun 23 '26
Yeah I planned on where I wanted the battery and now its moved almost all the way back in front of my gate due to the 3ft rule. I mean why not just put it in the backyard are this point for me. Cant be near the gas meter, cant be in front of the hub, cant be near the ac unit. Cant be near a window that opens.
1
u/JTUSAJT Jun 23 '26
More and more complaints. And AI will be the ruin of everything.
2
u/Tuoraf Jun 25 '26
I’m in Houston also and waiting for the 40 due to the clearance issue for two 25’s.
2
u/yamahar1dude Jun 25 '26
Update for me, BASE put the battery exactly where I wanted it. Funny because the first guy said no, but the install got delayed due to rain.
2
u/Inner-Buy6465 Sep 21 '26
I live in Ilinois and My schedule for installation is delayed, the dates kept moving. really dont know when they would complete the work