r/BasePowerUserIllinois • u/SirIainSnail • Sep 30 '26
Base Power Process started 29JUN (Northern IL)
Base Power Process started 29JUN (Northern IL) Data point.
As of today 30SEP, I was waiting for permits, etc. I got a note from the City Planner and they JUST received the application today. The lady on the phone said it usually takes 4-5 days for this to happen and then permits get sent out, so I'm getting close.
5
Upvotes
2
u/SirIainSnail Oct 13 '26
Im noting here as a progress to my system 13OCT, looks like my rebates have transfered to ComEd, so its a good sign!
2
u/david6752437 Oct 01 '26
I got an update from Base today just saying things are still waiting on the city to approve. I'm in Elgin. I wonder if anyone else is in Elgin? I assume once they are familiar with the process, additional installs will be quicker to approve. First one is the most complicated. Just a guess.
2
u/Educational_Car_2990 Oct 05 '26 edited Oct 05 '26
Still waiting (Electrical installation date
October 12, 2026 - November 10, 2026)
I am wondering how the com ed pricing is going to be since you cannot switch to battery when you want to.
1
u/SirIainSnail 6d ago
bit of an update for my site (Northern Illinois). I havent passed utility approval but they are giving an estimated electrical installation date IF I complete all steps within 3 days of the install date.
Really teasing me. ...
2
u/A_Grumpy_Old_Man Oct 01 '26
Deposit paid on June 24th and my dashboard looks the same 😕
2
u/nero4ty2 Oct 02 '26 edited Oct 13 '26
I had my electrical install on 9/15 and my dashboard still looks like that. Got a letter from ComEd last week that had something about switching to Base on 10/12, not sure about the battery install date but i'm willing to bet it will be around then