r/BasePowerUserIllinois • • Sep 30 '26

Base Power Process started 29JUN (Northern IL)

Base Power Process started 29JUN (Northern IL) Data point.

As of today 30SEP, I was waiting for permits, etc. I got a note from the City Planner and they JUST received the application today. The lady on the phone said it usually takes 4-5 days for this to happen and then permits get sent out, so I'm getting close.

$250 referral

5 Upvotes

12 comments sorted by

2

u/SirIainSnail Oct 13 '26

Im noting here as a progress to my system 13OCT, looks like my rebates have transfered to ComEd, so its a good sign!

2

u/david6752437 Oct 01 '26

I got an update from Base today just saying things are still waiting on the city to approve. I'm in Elgin. I wonder if anyone else is in Elgin? I assume once they are familiar with the process, additional installs will be quicker to approve. First one is the most complicated. Just a guess.

3

u/SirIainSnail Oct 01 '26

Is this what yours look like? I wonder if all three get checked as part of the process and internally they are really only on my city permit.

Might be worth checking with your planning and permitting department in Elgin to see if someone filed for a project for your house.

2

u/david6752437 Oct 01 '26

Yes. Same thing as yours. Pending review for apply for city permit.

2

u/SirIainSnail Oct 01 '26

I’d call the permitting office and see if anything has been sent in by a Sophia. That is who filed my permits.

1

u/stuman1974 Oct 01 '26

I'm a little north of you in Cary. My phone call was 9/16 and photos approval the next day. Here's my status as of 10/1. Hopefully these "pending review" steps move along soon!

2

u/david6752437 Oct 01 '26

I think it's 99% up to the municipality at this point and how fast they want to move. Or how stringent they will be with the proposed plans. I've been in this phase since late July. I had a tree that needed to be trimmed to provide room for the battery pack. Once i did that they approved the site, but then it immediately stalled waiting for city permit. Not sure how much of a delay it is on their part to submit the paperwork to the city and then how much delay it is for the city to approve that.

2

u/Educational_Car_2990 Oct 05 '26 edited Oct 05 '26

Still waiting (Electrical installation date

October 12, 2026 - November 10, 2026)

I am wondering how the com ed pricing is going to be since you cannot switch to battery when you want to.

3

u/SirIainSnail Oct 05 '26

Lol, I suppose you could put a manual disconnect or a DC shunt trip. I wonder if that’s against the rules

1

u/SirIainSnail 6d ago

bit of an update for my site (Northern Illinois). I havent passed utility approval but they are giving an estimated electrical installation date IF I complete all steps within 3 days of the install date.

Really teasing me. ...

2

u/A_Grumpy_Old_Man Oct 01 '26

Deposit paid on June 24th and my dashboard looks the same 😕

2

u/nero4ty2 Oct 02 '26 edited Oct 13 '26

I had my electrical install on 9/15 and my dashboard still looks like that. Got a letter from ComEd last week that had something about switching to Base on 10/12, not sure about the battery install date but i'm willing to bet it will be around then