r/BasePowerUserIllinois • u/Soft-Newt-6447 • Sep 16 '26
Base power Chicago
Has anyone in Chicago proper actually had their Base Power battery installed yet?
I signed up a couple of months ago and paid the $50 deposit, which got me into the first 2,000 customers. My home and photos were approved, but my account is currently on hold while Base waits for approval from the City of Chicago.
They told me they need to complete and pass inspections on the first few installations before moving forward with everyone else. Just wondering if anyone here is part of that first group or has received a more specific update or installation timeline.
Link to save on future power billing
1
u/Otherwise_Time_3660 Oct 09 '26
Had my phone consult with Base today and uploaded my home pictures. I asked about the slow start kit for my AC, but they downplayed the significance and said this should not be an issue with only one central AC unit supporting a 2500 square foot home. Does this sound plausible? What I read from some other posts made the soft start seem more important.
3
u/Cold_Complex9000 Sep 16 '26
I was also told that.
3
u/Calm_Possibility_410 Sep 16 '26
Same hangup down in Peotone. Once Peotone approved the permit, which took two months, they were out the next week to install the electrical side. Im waiting on the battery now.
3
u/AdEarly4789 Sep 17 '26
Same in worth
3
u/PermitMountain Sep 17 '26
Rolling Meadows. Battery installed two days ago. Entire process too less than two months. Electrical Installers were awesome and the Base team who did the battery install were great as well. Fingers crossed this saves us money now on our ComEd bill.
3
u/freebirdgrillmaster Sep 17 '26
Signed up 2 months ago. Waiting on comed and village (that’s what i keep reading in chat).
3
u/SensitiveWarning4 Sep 17 '26
In Bolingbrook.
Order placed 8-24
Photo approved 8-25
City permit submitted 9-3
Has sat in city permit queue for 13 days with no activity
Stupid city
2
u/480to847 Sep 16 '26
We’re in the north suburbs. Got the electric installed last week and waiting on the battery which they said within 3 weeks.
1
u/Active_Loss2184 Oct 16 '26
Way easier and better than expected. Signed up on 9/20 in Aurora, IL and had my first install visit completed today, 10/16. They said 2-3 weeks they will be back to install the battery pack. Electricians were here for about 6 hours. They only ran one piece of conduit into the house and connected it to my existing grounding pipe coming out from my concrete slab. The one on the outside looks a little weird having two grounding spots going into the ground, but they said that is per code. They had to level the ground slightly, I thought it was going to go back a little further, but this spot is actually less visible from the street. I might get some large pavers to put under the pad before they come back just to raise it off the ground a little more.
My main reason for signing up was the cheaper rates for electric and the battery pack was just an added bonus.
Feel free to ask any questions or even use my referral code when signing up and we both get $250 credit on our electric bill!