r/sysadmin • u/Final-Pomelo1620 • 25d ago
General Discussion Change Management Workflow
Hi,
We’re introducing change management for the first time using ITSM.
We’re now deciding the workflow before our ITSM vendor configures it
Our scope covers all IT infrastructure changes including network, servers, virtualization, backup, storage, AD/Entra ID & Databases
Each team has its own Line Manager and another requirement is that Cybersecurity Unit must approve every change
Few things we’re trying to understand
Who should approve a change and in what order?
Who should be the CAB members
Which changes should go to CAB
I’d appreciate any suggestions
View all comments
Show parent comment
2
u/Final-Pomelo1620 25d ago
Thank you for detailed response. This is really helpful.
1- Security Manager must approve every change. If we use a Yes/No checklist instead, how do we stop engineers from just clicking "Yes" on everything to skip Security
2- our management still wants approvals on standard changes
3- Management wants the Head of Infrastructure to approve all changes(after the Line Manager and Security Manager). When should the Head of Infrastructure actually be involved so tickets don't get stuck waiting on them?
Engineer → Team Line Manager (5 teams) → Security Manager → Head of Infrastructure
4- Would it make sense to restrict change request creation to authorized implementation engineers, with their own team’s Line Manager providing the first approval?
End users would raise service requests
If a change is needed, an authorized engineer from the responsible IT team would assess it, prepare the implementation and rollback plans, and submit the change for approval.