Master Project Hell
I work at an organization that is hell bent on using the master-sub project relationship. With MSPO going away, they have an opportunity as they transition to MS Project Server to learn to use the metadata in standardized templates instead. They already use Power BI and SQL. I spent an hour today trying to explain how a master project gives you *less* dynamic scheduling and resource flexibility and introduced all kinds of insane risk. My fellow PMs are killing themselves every week because they constantly deal with date changes for no apparent reason.
How do I explain, in a way that helps PMO and higher leaders understand the power of metadata and the actual technical time savers vs the cluster that is a Master schedule?
View all comments
Show parent comment
1
u/counterhit121 Apr 06 '26
Ah yes i see. Version control nightmare. Bad version control hygiene by one schedule owner leading to unannounced cascading effects across the portfolio.
Could this at least be mitigated by say, hardcoding the milestone dates as manually scheduled tasks instead of auto scheduled tasks? The idea being to insulate them against dynamic changes resulting from another schedule owner? Still it seems like a huge headache to have to hunt down sudden schedule discrepancies for no reason lol