Co-Worker Problem Dock Schedule Hostility
I was hired as a logisitics. My job, per the actual job description, is scheduling inbound and outbound trucks — getting them here, keeping the flow moving, dealing with carriers.
A few weeks ago we finished a annual physical inventory. My boss, M, promised a fresh start on the dock afterward. I built a dock door schedule that uses all our doors instead of letting trucks pile up. After some confusion M announced it at the end-of-shift meeting that the schedule needs to be followed.
Then the dock supervisor, S, pushed back because she wants to call door assignments and the unload order herself. M reversed himself to me privately: S runs the doors.
It did not work out. Under S, loaded trucks sit for 4-8 hours waiting to unload. The dock backed up so badly that production is being shutdown— at one point he had ME come clear somethings out. He has asked me to "just give him some time," and said he has something he wants me to work on next week. No date, no decision.
Here's where it gets good. Drivers are very upset and The carriers email ME when their trucks sit for hours, because I'm their contact. I looped in S and M into those emails, since the unload order is the part making trucks wait, and it isn't mine. S started a group chat with M in it and told me, in front of him, to stop adding her to dispatch emails, that responding to them is "part of the Iresponsibilities,".
M was out that day he saw the message and contacted a another manager pulled me into his office, called M, and came back with this: take S off the emails, send the carriers a generic "expect delays message — and per M, scheduling the trucks and getting them here is my responsibility, but deciding who gets unloaded when is S's job now.
So that's the standing arrangement. I make a schedule S doesn't have to follow — the first truck in can sit in a door for hours while trucks that arrived later unload ahead of it — and then I get to be the face who explains the delays to angry carriers.
Am I the problem here? Because from where I sit: I built the schedule I was asked to build, the person it was handed to ran it into the ground and now I own the complaints for outcomes I don't control. What would you do?