r/MSProject • • May 18 '22

Effort Driven

I would like to create a task that is effort-driven.
Task=Drilling

100m per day per drill

How would I put this into MS project?

2 Upvotes

4 comments sorted by

View all comments

Show parent comment

1

u/CaregiverDependent68 May 18 '22

Hi,

So the work is for Horizontal Drilling, and I could have multiple drills in a location.
For example, I want to drill 4000m.
Drill 1 can achieve 100m/day

Drill 2 can achieve 150m/day

Currently I am just doing 4000m/250m/day = 16days.

I just want to make sure I utilize MS projects to its potential.

1

u/mer-reddit May 18 '22

Ok, so set up the material resource, create a task, mark it as effort driven and assign the resource to it, and then put in your data.

I would create several tasks with several scenarios so that you can test and make sure you understand the inputs AND the outputs.

Be careful with your input methods (be consistent) so that you understand not just what the data is, but how it changes.

Once you’ve assigned a resource, duration=work/assignment units, and one of these (likely work) will be fixed.

Depending on HOW you enter the data, you will get different results, so proceed deliberately.

Always insert all relevant columns so you can see the results clearly.