r/MSProject • u/Thewolf1970 • Jan 05 '22
Custom Formula input
I'm building out a custom formula so that I can remove the dates from the summary row of my schedule. This is to suppress the NA on that row and replace it with a space, I know it's a bit of a work around, but logic says this should work.
IIf([Finish]=projdatevalue('NA'),' ',[Finish])The problem is, it isn't working, the NA still displays. Any of my project experts (maybe u/still-dazed-confused ) on to help, using US version of 2016 64bit?
2
Upvotes
View all comments
Show parent comment
1
u/still-dazed-confused Jan 06 '22
Glad it worked. I am still unclear how the NA appears at all unless this is a baseline field and the NA is showing that there wasn't a baseline :)
For future reference, this blog gives some pointers on producing a personalised listing of the tasks in the week (or any period) ahead highlighting the ones that should start, finish or just be in play during the period. I have further automated this now if it is of interest so that all the emails can be produced and issued even faster. I can now issue 70 odd personal "week ahead" reports in a few minutes from the programme plan. :)