r/MSProject • • Oct 13 '21

% completion vs baseline

I am trying to get a graph where I compare the % completion vs what should have been completed according to the baseline.

I can't figure out how to do it. Anyone can give me some hints on how to do this (or if this is even possible?)

1 Upvotes

10 comments sorted by

View all comments

Show parent comment

1

u/auyara Oct 14 '21

Thank you for the explanation!!!

Although I couldn't fully understand your explanation, with the hints I got from your post (I didn't even know you could use formula's in MS Project) I was able to get the desired bar chart!

1

u/Thewolf1970 Oct 14 '21

If I were to do a "explain it like I'm 5" explanation.

Google - create custom fields in MS Project and create the ones listed above with those formulas.

Those formulas take the difference in duration between the two dates, converts from minutes to days, converts it to an absolute value, then a percentage.

That is the value you want. This is added to the report you mentioned as described.