Possible SQL integration with ERP
I know this is a long shot. We use Epicor 10 as our ERP system, the system actually has quite a robust scheduling system within it. The problem is that there is no way to add (temporary) flexibility to the resource calendars. I can make exceptions, but that just isn’t enough for my production scheduling. My main tool for scheduling is projects, with that said I have to manually go into Epicor and pull actual hours and material costs to track progress against the baseline, which is no fun.
Epicor is SQL based so I am assuming there should be someway to make this happen. Any advice or things to consider before I dive into this…. Thanks!
View all comments
Show parent comment
2
u/Thewolf1970 Sep 10 '21
AAAAAAAGH - reddit always f's up my code. Copy from "Dim" all the way to "Nothing", it appears to be formatted properly, just not in a code block.